CA2555403C - Connection system for subsea flow interface equipment - Google Patents

Connection system for subsea flow interface equipment Download PDF

Info

Publication number
CA2555403C
CA2555403C CA2555403A CA2555403A CA2555403C CA 2555403 C CA2555403 C CA 2555403C CA 2555403 A CA2555403 A CA 2555403A CA 2555403 A CA2555403 A CA 2555403A CA 2555403 C CA2555403 C CA 2555403C
Authority
CA
Canada
Prior art keywords
conduit
frame
choke body
choke
connection
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CA2555403A
Other languages
French (fr)
Other versions
CA2555403A1 (en
Inventor
Ian Donald
John Reid
Alan Crawford
Paul W. White
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
OneSubsea IP UK Ltd
Original Assignee
Cameron Systems Ireland Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Family has litigation
First worldwide family litigation filed litigation Critical https://patents.darts-ip.com/?family=34911011&utm_source=google_patent&utm_medium=platform_link&utm_campaign=public_patent_search&patent=CA2555403(C) "Global patent litigation dataset” by Darts-ip is licensed under a Creative Commons Attribution 4.0 International License.
Application filed by Cameron Systems Ireland Ltd filed Critical Cameron Systems Ireland Ltd
Publication of CA2555403A1 publication Critical patent/CA2555403A1/en
Application granted granted Critical
Publication of CA2555403C publication Critical patent/CA2555403C/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B41/00Equipment or details not covered by groups E21B15/00 - E21B40/00
    • E21B41/0007Equipment or details not covered by groups E21B15/00 - E21B40/00 for underwater installations
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/02Surface sealing or packing
    • E21B33/03Well heads; Setting-up thereof
    • E21B33/04Casing heads; Suspending casings or tubings in well heads
    • E21B33/047Casing heads; Suspending casings or tubings in well heads for plural tubing strings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B33/00Sealing or packing boreholes or wells
    • E21B33/02Surface sealing or packing
    • E21B33/03Well heads; Setting-up thereof
    • E21B33/068Well heads; Setting-up thereof having provision for introducing objects or fluids into, or removing objects from, wells
    • E21B33/076Well heads; Setting-up thereof having provision for introducing objects or fluids into, or removing objects from, wells specially adapted for underwater installations
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/12Methods or apparatus for controlling the flow of the obtained fluid to or in wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/16Enhanced recovery methods for obtaining hydrocarbons
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/16Enhanced recovery methods for obtaining hydrocarbons
    • E21B43/162Injecting fluid from longitudinally spaced locations in injection well
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B43/00Methods or apparatus for obtaining oil, gas, water, soluble or meltable materials or a slurry of minerals from wells
    • E21B43/16Enhanced recovery methods for obtaining hydrocarbons
    • E21B43/166Injecting a gaseous medium; Injecting a gaseous medium and a liquid medium

Abstract

A connection system for connecting flow interface equipment to a subsea manifold is disclosed. The connection system relates particularly to a connection apparatus adapted to land a conduit means on a subsea manifold in a first stage of the connection and to connect a conduit means of the connection apparatus to a choke body of the manifold in a second stage of the connection.

Description

I Connection System for Subsea Flow Interface 2 Equipment 4 This invention relates in general to subsea well production, and in particular to a connection system 6 far connecting flow interface equipment, such as a 7 pump to a subsea Christmas tree assembly.

9 A subsea production facility typically comprises a subsea Christmas tree with associated equipment.
11 The subsea Christmas tree typically comprises a 12 choke located in a choke body in a production wing 13 branch. There may also be a further choke located 14 in an annulus wing branch. Typically, well fluids 25 leave the tree via the production choke and the 16 production wing branch into an outlet flowline of 17 the well. However, in such typical trees, the 18 fluids leave the well unboosted and unprocessed.
l9 According to a fixst aspect of the present invention 21 there is provided an apparatus for connecting to a 1 subsea wellbore, the wellbore having a manifold and 2 a choke body, the apparatus comprising:
3 a frame adapted to land on the manifold;
a conduit system having a first end for connection to the interior of the choke body and a 6 second end for connection to a processing apparatus;
7 wherein the conduit system comprises a conduit 8 means supported by the frame;
9 wherein the frame comprises at least one frame member that is adapted to land on the manifold in a 11 first stage of the connection and wherein the 12 conduit means is adapted to be brought into fluid 13 communication with the interior of the choke body in 14 a second stage of the connection.
16 The two-stage connection provides the advantage that 1'7 damage to the mating surfaces between the conduit 18 means and the flow line of the tree assembly can be 19 avoided whilst the frame is being landed, since at least a part of the frame is landed before the 21 connection between the conduit means and the 22 interior of the choke body is made up. Hence, the 23 two-stage connection acts to buffer and protect the 24 mating surfaces. The two-stage connection also protects the choke itself from damage whilst the 26 frame is being landed; in particular, the mating 27 surface of the choke is protected.

29 Zn some embodiments, processing apparatus e.g.
mufti-phase flow meters and pumps can be mounted on 31 the frame and can be landed on the tree with the 32 frame. Alternatively, the processing apparatus may l be located remote from the tree, e.g. on a further 2 subsea installation such as a manifold or a pile, 3 and the frame may comprise connections for jumper conduits which can lead fluids to and from the remote processing apparatus.

7 The processing apparatus allows well fluids to be 8 processed (e. g. pressure boosted/ injected with 9 chemicals) at the wellhead before being delivered to 20 the outlet flowline of the well. The invention may 11 alternatively be used to inject fluids into the well 12 using the outlet flowline as an inlet.

14 Often the processing apparatus, e.g. subsea pump, flow meter, etc. is quite heavy and bulky. In 16 embodiments where heavy/bulky apparatus is carried l7 by the frame, the risk of damage to the mating 18 surfaces between the conduit means and the flow line 19 of the tree assembly is particularly great.
21 Optionally, the apparatus further comprises an 22 actuating means mounted on the frame, the actuating 23 means being adapted to bring the conduit means into 24 fluid communication with the interior of the choke body. Typically, the actuating means comprises at 26 least one hydraulic cylinder. Alternatively, the 27 actuating means may comprise a cable or a screw jack 28 which connects the conduit means to the frame, to 29 control the movement of the conduit means relative to the frame, 1 the conduit means is not necessarily brought into 2 direct communication with the choke body. In some 3 embadiments (the first embodiment and the third 4 embodiment below), the conduit means is connected with the~interior of the choke body via a further, 6 secondary conduit.

8 In a first embodiment, a mounting apparatus is 9 provided for landing a flow interface device, particularly a subsea pump or compressor (referred 11 to collectively at times as "pressure intensifier") 12 on a subsea production assembly.

14 Optionally, the at least one frame member of the first connection stage comprises a lower frame 16 member, and the apparatus further comprises an upper 17 frame member, the upper f came member and the lower l8 frame member having co-operating engagement means 19 for landing the upper frame member on the lower frame member.

22 In the first embodiment, a secondary conduit in the 23 form of a mandrel with a flow passage is mounted to 24 the lower frame member. The operator lowers the lower frame member into the sea and onto the 26 production assembly. The production assembly has an 27 upward facing receptacle that is sealingly engaged 28 by the mandrel.

In this embodiment, the conduit means comprises a 31 manifold, which is mounted to the upper frame 32 member. The manifold is connected to a flow l interface device such as a pressure intensifier, 2 which is also mounted to the upper frame member.
3 The operator lowers the upper frame member along 4 with the manifold and pressure intensifier into the 5 sea and onto the lower frame member, landing the 6 manifold on the mandrel. During operation, fluid 7 flows from the pressure intensifier through the 8 manifold, the mandrel, and into the flow line.
Preferably, the subsea production assembly comprises Z1 a Christmas tree with a frame having guide posts.
Z2 The operator installs extensions to the guide posts, l3 if necessary, and attaches guidelines that extend to 14 a surface platform. The lower and upper frame members have sockets with passages for the 16 guidelines. The engagement of the sockets with the 17 guide posts provides gross alignment as the upper 18 and lower frame members are lowered onto the tree 19 frame.
21 Also, preferably the Christmas tree frame has upward 22 facing guide members that mate with downward facing 23 guide members on the lower frame member for 24 providing finer alignment. Further, the lower frame member preferably has upward facing guide members 26 that mate with downward facing guide members on the 27 upper frame member for providing finer alignment.
28 One or more locking members on the lower frame 29 member lock the lower frame member to the tree frame. Additionally, one or more locking members on 31 the upper frame member lock the upper frame member 32 to the lower frame member.

2 Optionally, the apparatus further comprises 3 buffering means provided on the frame, the buffering 4~ means providing a minimum distance between the frame and the tree.

7 The buffering means may comprise stops or adjustable 8 mechanisms, which may be incorporated with the 9 locking members, or which may be separate from the lacking members.

12 The adjustable stops define minimum distances 13. between the lower frame member and the upper plate 14 of the tree frame and between the lower frame member and the upper frame member.

17 The buffering means typically comprise threaded 18 bolts, which engage in corresponding apertures in 19 the frame, and which can be rotated to increase the length they project from the frame. The ends of the 21 threaded bolts typically contact the upper frame 22 member of the tree, defining a minimum distance 23 between the frame and the tree.

Optionally, a further buffering means is provided 26 between the lower and upper frame members to define 27 a minimum distance between the lower and upper frame 28 members. The further buffering means also typically 29 comprises threaded bolts which extend between the lower and upper frame members. The extent of 31 projection of the threaded bolts can be adjusted to 1 provide a required separation of the upper and lower 2 frame members.

4 The buffering means (e. g. the adjustable stops) provides structural load paths from the pper frame u 6 member through the ower frame member and tree frame l 7 to the tree and the wellhead on which the tree is 8 mounted. These load paths avoid structur al loads 9 passing through the mandrel to the upward facing receptacle (i.e. the choke body).

12 In a second embodiment, the frame is lowered as a 13 unit, but typically has an upper portion (an upper 14 frame member) that is vertically movable relative to the lower portion (a lower frame member). A
16 processing apparatus (in the form of a pressure 17 intensifier) and a conduit means (a mandrel) are 18 mounted to the upper portion. An actuating means 19 comprising one or more jack mechanisms is provided between the lower and upper portions of the frame.
21 When the lower portion of the frame lands on the 22 tree frame, the lower end of the mandrel will. be 23 spaced above the flow line receptacle. The jack 24 mechanisms then lower the upper portion of the frame, causing the mandrel to stab sealingly into 26 the receptacle (the choke body). Thus, in this 27 embodiment, the conduit means comprises a single 28 mandrel having a single flowpath therethrough.

In a third embodiment, the conduit means has a 31 flexible portion. Preferably, the flexible portion 32 is moveable relative to the frame. Typically, the 1 flexible portion of the conduit means is fixed 2 relative to the frame at a single point. Typically, 3 the flexible portion of the conduit means is 4 connected to the processing apparatus and supported at the processing apparatus connection, in 6 embodiments where the processing apparatus is 7 supported on the frame.

9 Optionally, the conduit means comprises two conduits, one of which is adapted to carry fluids 11 going towards the processing apparatus, the other 12 adapted to carry fluids returning from the 13 processing apparatus. Typically, each of the two 14 conduits of the conduit means is fixed relative to the frame at a respective point. Typically, the 16 flexible portion of each of the two conduits of the 1'7 conduit means is connected to the processing 18 apparatus and is supported at the processing 19 apparatus connection (where a processing apparatus is provided on the frame).

22 Typically, the flexible portion of the conduit means 23 is resilient. Typically, the direction of movement 24 of the flexible portion of the conduit means in the second stage of the connection defines an axis of 26 connection and the flexible portion of the conduit 27 means is curved in a plane perpendicular to the axis 28 of connection to provide resilience in the 29 connection direction. Tn such embodiments, the flexible portion of the conduit means is in the form 31 of a coil, or part of a coil. This allows the lower 2 end of the conduit means (the connection end) to be 2 moved resiliently in the connection direction.

g Typically, the flexible portion of the conduit means supports a connector adapted to attach to the choke 6 body (either directly or via a further conduit 7 extending from the choke body), the flexible portion 8 of the conduit means allowing relative movement of 9 the connector and the frame to buffer the connection.

l2 Typically, an actuating means is provided which is l3 adapted to move the flexible portion relative to the l4 frame to bring an end of the flexible portion into fluid communication with the interior of the choke 16 body. The actuating means typically comprises a 17 swivel eye mounting hydraulic cylinder.

19 Considering now all embodiments of the invention, the conduit system may optionally provide a single 21 flowpath between the choke body and the processing 22 apparatus.

24 Alternatively, the conduit system provides a two-flowpath system: a first flowpath from the choke 26 body to the processing apparatus and a second 27 flowpath from. the processing apparatus to the choke 28 body. In such embodiments, the conduit system can 29 comprise a housing and an inner hollow cylindrical member, the inner cylindrical member being adapted 31 to seal within the interior of the choke body to 32 define a first flow region through the bore of the 1 cylindrical member and a second separate flow region 2 in the annulus between the cylindrical member and 3 the housing.

5 Typically, the first and second flow regions are 6 adapted to connect to a respective inlet and an 7 outlet of the processing apparatus.

9 Such embodiments can be used to recover fluids from 10 the well via a first flowpath, process these using 11 the processing apparatus (e. g. pressure boosting) 12 and then to return the fluids to the choke body via l3 a second flowpath for recovery through the 14 production wing branch. The division of the inside l5 of the choke body into first and second flow regions I6 by the inner cylindrical member allows separation of 17 the first and second flowpaths within the choke 18 body.

If used, the housing and the inner hollow 21 cylindrical member typically are provided as the 22 part of the conduit system that directly connects to 23 the choke body, i.e. in the first embodiment, this 24 is the secondary conduit; in the second embodiment, the conduit means, and in the third embodiment, the 26 secondary conduit.

28 Optionally, the processing apparatus is provided on 29 the frame. In this case, the processing apparatus is typically connected to the conduit means before 31 the frame is landed on the tree.

1 Alternatively, the processing apparatus is provided 2 on a further subsea manifold, such as a suction 3 pile. Jumper cables can be connected between the 4 fxame on the manifold and the further subsea manifold to connect the processing apparatus to the 6 conduit system. In this case, the processing 7 apparatus as typically connected to the conduit 8 means as a final step.

In all embodiments, the frame typically includes 11 guide means that co-operate with guide means 12 provided on the manifold, to align the frame with 13 the manifold. The frame may also or instead 14 comprise a guide pipe that surrounds at least a part of the conduit system, to protect it from impact 26 damage.

18 A11 embodiments use the space inside the choke body 19 after the choke bonnet has been removed and the choke withdrawn. However, it may still be desirable 21 to be able to use a choke to control the fluid flow.
22 Optionally, a replacement choke is provided on the 23 frame, the replacement choke being connectable to 24 the conduit system.
26 Embodiments of the invention can be used for both 27 recovery of production fluids and injection of 28 fluids.

According to a second aspect of the present 31 invention there is provided a method of connecting a 32 processing apparatus to a subsea wellbore, the 1 wellbore having a manifold and a choke body, the 2 method comprising:
3 landing a frame on the manifold and connecting 4 a conduit system between the choke body and the processing apparatus, the frame supporting a conduit 6 means of the conduit system;
7 wherein the frame comprises at least one frame 8 member that is landed on the manifold in a first 9 connection stage, and wherein the conduit means is brought into fluid communication with the interior l1 of the choke body in a second connection stage.
l2 13 The method typically includes the initial steps of 14 removing the choke bonnet and connecting the secondary conduit to interior of the choke body.
l6 17 The choke bonnet is removed and the secondary 18 conduit may be installed by choke bonnet changing 19 equipment (e. g. the third embodiment).
Alternatively, the secondary conduit may be 21 supported on the lower frame member and may be 22 installed when the lower frame member is landed on 23 the manifold (e. g. the first embodiment).

According to a third aspect of the present invention 26 there is provided an apparatus for connecting toga 27 subsea wellbore, the wellbore having a manifold and 28 a choke body, the apparatus comprising:
29 a frame having a conduit system, the frame being adapted to land on the tree, the conduit 31 system including a first end which is adapted to 32 connect to the choke body such that the conduit is 1 in fluid communication with the interior of the 2 choke body, and a second end connectable to a 3 processing apparatus;
4 wherein the frame comprises buffering means adapted to buffer the connection between the first 6 end of the conduit system and the choke body.

8 In the first embodiment, the buffering means may be 9 provided by the adjustable stop means, which provide structural load paths from the upper frame member Z1 through the lower frame member and tree frame to the 12 tree and the wellhead on which the tree is mounted 23 which avoid structural. loads passing through the 14 mandrel to the choke body.
16 In the second embodiment, the buffering means is 17 typically provided by the arrangement of the upper 18 and lower frame members, the upper frame member 19 being moveable to lower the mandrel (the conduit means) into connection with the choke body in a 21 controlled manner, only after the frame has been 22 landed.

24 In the third embodiment, the buffering means may be provided by the flexible portion of the conduit 26 means, which allows movement of the conduit end that 27 connects to the secondary conduit. Therefore, the 28 connection end of the conduit means will not heavily 29 impact into the secondary conduit as it is able to deflect as necessary, using the flexibility of the 31 conduit means, and can optionally be manoeuvred for 1 even greater control (e. g. by an actuating 2 mechanism).

4 According to a fourth aspect of the present invention there is provided an apparatus for 6 connecting to a subsea wellbore, the wellbore having 7 a manifold and a choke body, the apparatus 8 comprising:
9 a frame adapted to land on the manifold;
a conduit system having a first end for l1 connection to the choke body and a second end for 12 connection to a processing apparatus;
13 wherein at least a part of the conduit system 14 is supported by the frame;
l5 wherein the conduit system comprises at least 16 one flexible conduit having an end that is moveable 17 relative to the frame to make up a communication l8 between the processing apparatus and the choke body.

In such embodiments, the end of the flexible conduit 21 can deflect if it impacts with the choke body (or 22 any secondary conduit extending from the choke 23 body). Thus in such embodiments, the flexible 24 conduit ensures that the load carried by the frame is not transferred to the choke body.

27 Embodiments of the invention will now be described, 28 by way of example only, and with reference to the 29 following drawings, in which:-31 Figure 1 is an elevational view of a subsea tree 32 assembly, partially in section, and showing an 1 apparatus for connecting a f~.ow interface to a 2 subsea wellbore;

4 Figure 2 is an enlarged view, partially in section, 5 of a choke body of the tree assembly and a lower 6 portion of a mandrel of the apparatus of Figure 1;

8 Figure 3 is a top view of the tree frame of Figure 9 1, with the connecting apparatus for the flow 10 interface device removed;

12 Figure 4 is a top view of a lower frame member of 13 the connecting apparatus of Figure Z;

l5 Figure 5 is a sectional view of the lower frame l6 member of Figure 4, taken along the line 5-5 of 17 Figure 4;

19 Figure 6 is a top view of an upper frame member of the connecting apparatus of Figure 1;

22 Figure 7 is a partially sectioned view of the upper 23 frame member of Figure 6, taken along the line 7-7 24 of Figure 6;
26 : Figure 8 is a schematic view of an alternate 27 embodiment of a connecting system, shown prior to 28 landing on the subsea tree assembly;

Figure 9 is a schematic View of the mounting system 31 of Figure 8, with a lower frame member of the Z connecting system landed on the subsea tree assembly 2 and the upper frame member in an upper position;

4 Figure 10 is a schematic view of the subsea tree assembly and the connecting system of Figure 8, with 6 the upper frame member in a lower position;

8 Fig 11 is a side view with interior details of a 9 third embodiment of the invention;
l0 11 Fig 12 is an enlarged view in cross-section of a 12 portion A of the Fig 11 embodiment;

14 Fig 13 is a plan view of the Fig 11 embodiment;
16 Fig l4 shows a series of views with cross-sectional l7 details showing the Fig 11 apparatus being installed 18 on a manifold;

Fig 15 shows an enlarged view of Fig 14D;

22 Fig 16 shows a side view of an embodiment similar to 23 that of Fig 11, the frame also supporting a 24 replacement choke; and 26 Fig 17 shows an alternative embodiment similar to 27 that of Fig 16, wherein an actuating means is 28 provided to control the movement of a conduit means.

Referring to Figure 1, production assembly 11 in 31 this example includes a subsea Christmas tree 13.
32 Christmas tree 13 is a tubular member with a tree 1 connector 15 on its lower end that connects to a 2 wellhead housing (not shown) located on the sea 3 floor. Tree 13 may be conventional, having a 4 vertical bore with a master valve I7 and a swab valve 19. A production passage in tree 13 leads 6 laterally to a production wing valve 21. Tree 13 7 may be either a type having a tubing hanger landed 8 within, or it may be a type in which the tubing 9 hanger lands in the wellhead housing below the tree.
11 A production choke body or receptacle 23 mounts to 12 production wing valve 21. Choke body 23 comprises a 13 housing for a choke insert (not shown) that is 14 adjustable to create a back pressure and a desired flow rate. Choke body 23 conneots to a production 16 flow line 25 that leads to sea floor processing 17 equipment or directly to a production facility at 18 sea level. After being installed with a pressure 19 intensifier, as will be subsequently explained, a choke insert may not be required. One use for the 21 connecting apparatus of this invention is to 22 retrofit existing trees that have previously 23 operated without a pressure intensifier.

Tree 13 may also have an annulus valve 27 that 26 communicates with a tubing annulus passage (not 27 shown) in the well. An annulus choke 29 connects to 28 annulus valve 27 for controlling a flow rate either 29 into or out of the tubing annulus. Annulus choke 29 is normally located on a side of production assembly 31 11 opposite production choke body 23. Annulus choke 1 29 has a body with a choke insert similar to 2 production choke body 23.

4 A tree cap 31 releasably mounts to the upper end of tree 13. A tree frame 33 extends around tree l3 for 6 mounting various associated equipment and providing 7 protection to tree 23 if snagged by fishing nets.
8 Tree frame 33 is structurally connected to the body 9 of tree 13, such that weight imposed on tree frame 33 transfers to tree 13 and from there to the 11 wellhead housing (not shown) on which tree 13 is 12 mounted. Tree frame 33 has an upper frame member 13 portion or plate 35 that in this instance is located 14 above swab valve 19 and below tree cap 31. Upper plate 35 surrounds tree 13, as shown in Figure 3, 16 and is generally rectangular in configuration. Tree 17 frame upper plate 35 has a cutout 36 that provides 18 vertical access to choke body 23 and a cutout 38 19 that provides vertical access to annulus choke 29.
21 As shown in Figure 3, preferably tree frame upper 22 plate 35 has a plurality of guide members 37. Guide 23 members 37 may vary in type, and prior to 24 retrofitting with a pressure intensifier, were used to land equipment for retrieving and replacing the 26 choke insert (,not shown) in choke body 23 and in 27 annulus choke 29. Although some subsea trees do not 28 have any type of guide members, many do, 29 particularly trees installed during the past 10-15 years. In this example, each guide member 37 31 comprises an upward facing cylinder with an open 32 top. Guide members 37 are mounted in pairs in this 1 example with a locking member 39 located between 2 them. Locking member 39 has a .latch that latches 3 onto a locking member inserted from above. Four 4 separate sets of guide members 37 are shown in Figure 3, with one set located on opposite sides of 6 cutout 36 and the other sets on opposite sides of 7 cutout 38.

9 Figure 3 also shows a control pod receptacle 40 that may be conventional. Control pod receptacle 40 has 11 guide members 37 and locking members 39 for landing 12 an electrical and,hydraulzc control pod (not shown) 13 lowered from sea level. A plurality of guide posts 14 41 are located adjacent sides of tree frame 33.
Typically, each guide post 41 is located at a corner 16 of tree frame 33, which .is generally rectangular in 17 configuration. Only one guide post 41 is shown in 18 Figure 1, but the other three are the same in 19 appearance. The existing guide posts 41 likely may not be long enough for the retrofit of a pressure 21 intensifier in accordance with this invention. If 22 so, a guide post extension 42 is installed over each 23 guide post 41, and becomes a part of each guide post 24 41. Guide post extensions 42 protrude upward past tree cap 31. A guideline 43 with a socket on its 26 lower end slides over and connects to each guide 27 post 41 or guide post extension 42, if such are 28 used. Guidelines 43 extend upward to a platform or 29 workover vessel at sea level.
31 Still referring to Figure 1, a flow interface device 32 lower frame member 45 lands on and is supported by 1 tree frame upper plate 35_ In this embodiment, 2 lower frame member 45 is a flat generally 3 rectangular member, as shown in Figure 4, but it 4 need not be a flat plate. A mandrel 47 is secured 5 to one side of lower frame member 45. Mandrel 47 6 has a tubular lower portion with a flange 49 that 7 abuts and seals to a mating flange on choke body 23.
8 Alternatively, mandrel 47 could be positioned on an 9 opposite edge of lower frame member 45 and mate with 10 the body of annulus choke 29, rather than choke body 11 23.

13 A clamp 51 locks flange 49 to the flange of choke 14 body 23. Clamp 51 is preferably the same apparatus 15 that previously clamped the choke insert (not shown) 16 into choke body 23 when production assembly 11 was 17 being operated without a pressure intensifier.
18 Clamp 51 is preferably actuated with an ROV (remote 19 operated vehicle) to release and actuate clamp 51.
21 Referring to Figure 2, mandrel 47 has a lower bore 22 52 that aligns with choke body vertical bore 53. A
23 retrievable plug 55 is shown installed within a 24 lower portion of choke vertical bore 53. A lateral passage 57 leads from choke body vertical bore 53 26 above plug 55 to production wing valve 21 (Figure 27 1). Plug 55 prevents fluid flowing down through 28 mandrel 47 from entering flow line 25. Some 29 installations have a valve in flow line 25 downstream of choke body 23. If so, plug 55 is not 31 required.

1 Referring to Figure 5, lower frame member 45 has a 2 plurality of guide members 67 on its lower side that 3 mate with guide members 37 of tree frame upper plate 4 35 as show in Figure 3. Only one of the sets of guide members 67 is shown, and they are shown in a 6 schematic form. Furthermore, a locking member 69 7 protrudes downward from lower frame member 45 for 8 locking engagement with one of the locking members 9 39 (Figure 3) of tree frame upper plate 35. Lock member 69 is also shown schematically. Other types l1 of Locks are feasible.

13 Lower frame member 45 also has guide post sockets 14 71, each preferably being a hollow tube with a downward facing funnel on its lower end. Guide post 16 sockets 71 slide over guide lines 43 (Figure 1) and 17 guide posts 41 or extensions 42. Guide posts 41 or 18 their extensions 42 provide a gross alignment of 19 mandrel 47 with choke body 23 (Figure 2). Guides 67 and 37 (Figure 1) provide finer alignment of mandrel 21 47 with choke body 23 (Figure 1).

23 Referring still to Figure 5, lower frame member 45 24 also preferably has a plurality of upward facing guide members 75. In this example, guide members 75 26 are the same type as guide members 37 (Figure 3), 27 being upward facing cylinders with open tops. Other 28 types of guide members may be utilised as well. In 29 this instance, preferably there are four sets of guide members 75, with each set comprising two guide 31 members 75 with a locking member 77 located between 32 as shown in Figure 4. Guide members 75 are located 1 in vertical alignment with guide members 37 (Figure 2 3), but could be positioned elsewhere. Tower frame 3 member 45 also has a cutout 79 on one side for 4 providing vertical access to annulus choke 29 (Figure 3).

7 An adjustment mechanism or mechanisms (not shown) 8 may extend between lower frame member 45 and tree 9 frame upper plate 37 to assure that the weight on lower frame member 45 transfers to tree frame upper 11 plate 37 and not through mandrel 47 to choke body 12 23. While the lower end of mandrel 47 does abut the 13 upper end of choke body 23, preferably, very little 14 if any downward load due to any weight on lower frame member 45 passes down mandrel 47 to choke body 16 23. Applying a heavy load to choke body 23 could 17 create excessive bending moments on the connection 18 of production wing valve 21 to the body of tree 13.
19 The adjustment mechanisms may comprise adjustable stops on the lower side of lower frame member 45 21 that contact the upper side of tree frame upper 22 plate 37 to provide a desired minimum distance 23 between lower frame member 45 and upper plate 37.
24 The minimum distance would assure that the weight on lower frame member 45 transfers to tree upper plate 26 35, and from there through tree frame 33 to tree 13 27 and the wellhead housing on which tree 13 is 28 supported. The adjustment mechanisms could be 29 separate from locking devices 69 or incorporated with them.

1 Referring to Figure 1, after lower frame member 45 2 lands and locks to tree frame upper plate 35, an 3 upper frame member 81 is lowered, landed, and locked 4 to lower frame member 45. Upper frame member 81 is also preferably a generally rectangular plate, but 6 it could be configured in other shapes. Upper frame 7 member 82 has a mandrel connector 83 mounted on an 8 upper side. Mandrel connector 83 slides over 9 mandrel 47 while landing. A locking member 85, which could either~be a set of dogs or a split ring, 11 engages a grooved profile on the exterior of mandrel 12 47. Locking member 85 locks connector 83 to mandrel 13 47. A hydraulic actuator 87 strokes locking member 14 85 between the locked and released positions.
Preferably, mandrel connector 83 also has a manual 16 actuator 89 for access by an R0V in the event of 17 failure of hydraulic actuator 87. A manifold 91 is 18 a part of or mounted to an upper inner portion of 19 mandrel connector 83. Manifold 91 has a passage 93 that sealingly registers with mandrel passage 52.

22 As shown by the dotted lines, a motor 95, preferably 23 electrical, is mounted on upper frame member 81. A
24 filter 97 is located within an intake line 98 of a subsea pump 99. Motor 95 drives pump 99, and the 26 intake in this example is in communication with sea 27 water. Pump 99 has an outlet line 101 that leads to 28 passage 93 of manifold 91.

As shown in Figure 6, upper frame member 81 has four 31 guide post sockets 103 for sliding down guidelines 32 43 (Figure 1) and onto the upper portions of guide 1 posts 41 or guide post extensions 42. Upper frame 2 member 81 has downward extending guide members 105 3 that mate with upward extending guide members 75 of 4 lower frame member 45, as shown in Figure 7.
Locking members 107 mate with locking members 77 6 (Figure 4) of lower frame member 45. Upper frame 7 member 81 has a central hole 109 for access to tree 8 cap 31 (Figure 1).

Adjustable mechanisms or stops (not shown) may also 1l extend between lower frame member 45 and upper frame 12 member 81 to provide a minimum distance between them l3 when landed. The minimum distance is selected to 14 prevent the weight of pump 99 and motor 95 from transmitting through mandrel connector 83 to mandrel 16 47 and choke body 23. Rather, the load path for the 17 weight is from upper frame member 81 through lower 1.8 frame member 45 and tree frame upper plate 35 to 19 tree 13 and the wellhead housing on which it is supported. The load path for the weight on upper 21 frame member 81 does not pass to choke body 23 or 22 through guide posts 41, The adjustable stops could 23 be separate from locking devices 107 or incorporated 24 with them.
26 In the operation of this example, production 27 assembly 11 may have been operating for some time.
28 either as a producing well, or an injection well 29 with fluid delivered from a pump at a sea level platform. Also, production assembly 11 could be a 31 new installation. Lower frame member 45, upper 32 frame member 81 and the associated equipment would 1 originally not be located on production assembly 11.
2 If production assembly 11 were formerly a producing 3 well, a choke insert (not shown) would have been 4 installed within choke body 23.

6 To install pressure intensifier 99, the operator 7 would attach guide post extensions 42, if necessary, 8 and extend guidelines 43 to the surface vessel or 9 platform. The operator removes the choke insert in 10 a conventional manner by a choke retrieval tool (not 11 shown) that interfaces with the two sets of guide 12 members 37 adjacent cutout 36 (Fig. 3). It 13 production assembly 11 lacks a valve on flow line 14 25, the operator lowers a plug installation tool on 15 guidelines 43 and installs a plug 55.

17 The operator then lowers lower frame member 45 along 18 guideline's 43 and over guide posts 41. While 19 landing, guide members 67 and lock members 69 20 (Figure 5) slidingly engage upward facing guide 21 members 37 and locking members 39 (Figure 1). The 22 engagement of guide members 37 and 67 provides fine 23 alignment for mandrel 47 as it engages choke body 24 23. Then, clamp 51 is actuated to connect the lower 25 end of mandrel 47 to choke body 23.
27 The operator then lowers upper frame member 81, 28 including pump 99, which has been installed at the 29 surface on upper frame member 81. Upper frame member 81 slides down guidelines 43 and over guide 31 posts 41 or their extensions 42. After manifold 91 32 engages mandrel 47, connector 83 is actuated to lock 1 manifold 91 to mandrel 47. Electrical power for 2 pump motor 95 may be provided by an electrical wet-3 mate connector (not shown) that engages a portion of 4 the control pod (not shown), or in some other manner. If the control pod did not have such a wet 6 mate connector, it could be retrieved to the surface 7 and provided with one.

9 Once installed, with valves 17 and 21 open, sea water is pumped by pump 99 through outlet Line 101, 11 and flow passages 93, 52 (Figure 2) into production 12 wing valve 21. The sea water flows down the well 13 and into the formation for water flood purposes. If 14 repair or replacement of pressure intensifier 99 is required, it can be retrieved along with upper frame 16 member 81 without disturbing lower frame member 45.

18 An alternate embodiment is shown in Figures 8-10.
19 Components that are the same as in the first embodiment are numbered the same. The mounting 21 system has a lower frame member or frame portion 111 22 and an upper frame member or frame portion 113.
23 Jack mechanisms, such as hydraulic cylinders 115, 24 extend between lower and upper frame members 111, 113. Hydraulic cylinders 115 move upper frame 26 member 113 relative to lower frame member 111 from 27 an upper position, shown in Figures 8 and 9, to a 28 lower position, shown in Figure 10. Lower frame 29 member 111 preferably has guide members on its lower side for engaging upward facing guides on tree frame 32 upper plate 35, although they are not shown in the 32 drawings.

2 Mandrel 117 is rigidly mounted to upper frame member 3 113 in this embodiment and has a manifold portion on 4 its upper end that connects to outlet line 101, which in turn leads from pressure intensifier or 6 pump 99. Mandrel 117 is positioned over or within a 7 hole 118 in lower frame member 111. When upper 8 frame member 113 moves to the lower position, shown 9 in Figure 10, mandrel 117 extends down into engagement with the receptacle of choke body 23.

12 Tn the operation of the second embodiment, pressure 13 intensifier 99 is mounted to upper frame member 113, 14 and upper and lower frame members 113, 111 are lowered as a unit. Hydraulic cylinders 115 will 16 support upper frame member 113 in the upper 17 position. Guidelines 43 and guide posts 41 guide 18 the assembly onto tree frame upper plate 35, as 19 shown in Figure 9. Guide members (not shown) provide fine alignment of lower frame member 111 as 21 it lands on tree frame upper plate 35. The lower 22 end of mandrel 117 will be spaced above choke body 23 23. Then hydraulic cylinders 115 allow upper frame 24 member 113 to move downward slowly. Mandrel 117 engages choke body 23, and clamp 51 is actuated to 26 clamp mandrel 117 to choke body 23. Locks (not 27 shown) lock lower and upper frame members 111, 113 28 to the tree frame of tree 13.

Figs l1 to 13 show a third embodiment of the 31 invention. Fig 11 shows a manifold in the form of a 32 subsea Christmas tree 200. The tree 200 has a 1 production wing branch 202, a choke body 204, from 2 which the choke has been removed, and a flowpath 3 leading to a production wing outlet 206. The tree 4 has an upper plate 207 on which are mounted four "John Brown" feet 208 (two shown) and four guide 6 legs 210. The guide legs 210 extend vertically 7 upwards from the tree upper plate 207. The tree 8 also supports a control module 205.

Figs 11 and 13 also show a frame 220 (e. g. a skid) 11 located on the tree 200. The frame 220 has a base 12 that comprises three elongate members 222 which are l3 cross-linked by perpendicular bars 224 such that the 14 base has a grid-like structure. Further cross-linking arched members 226 connect the outermost of 16 the bars 222, the arched members 226 curving up and 17 over the base of the frame 220.

19 Located at approximately the four corners of the frame 220 are guide funnels 230 attached to the base 21 of the frame 220 on arms 228. The guide funnels 230 22 are adapted to receive the guide legs 210 to provide 23 a first (relatively course) alignment means. The 24 frame 220 is also provided with four "John Brown"
legs 232, which extend vertically downwards from the 26 base of the frame 220 so that they engage the John 27 Brown feet 208 of the tree 200.

29 A processing apparatus in the form of a pump 234 is mounted on the frame 200. The pump 234 has an 31 outlet and inlet, to which respective flexible 32 conduits 236, 238 are attached. The flexible 1 conduits 236, 238 curve in a plane parallel to the 2 base of the frame 220, forming a partial loop that 3 curves around the pump 234 (best shown in Fig 13).
4 After nearly a complete loop, the flexible conduits 236, 238 are bent vertically downwards, where they 6 connect to an inlet and an outlet of a piping 7 interface 240 (to be described in more detail 8 below). The piping interface 240 is therefore 9 suspended from the pump 234 on the frame 220 by the flexible conduits 236, 238, and is not rigidly fixed 11 relative to the frame 220. Because of the 12 flexibility of the conduits 236, 238, the piping 13 interface 240 can move both in the plane of the base 14 of the frame 220 (i.e. in the horizontal plane of Fig 11) and in the direction perpendicular to this 16 plane (vertically in Fig 11). In this embodiment, 17 the conduits 236, 238 are typically steel pipes, and 18 the flexibility is due to the curved shape of the 19 conduits 236, 238, and their respective single points of suspension from the pump 234, but the 21 conduits could equally be made from an inherently 22 flexible material or incorporate other resilient 23 means.

A secondary conduit 250 is connected to the choke 26 body 204, as best shown in Fig 15. The secondary 27 conduit 250 comprises a housing 252 in which an 28 inner member 254 is supported. The inner member 254 29 has a cylindrical bore 256 extending therethrough, which defines a first flow region that communicates 31 with the production wing outlet 206. The annulus 32 258 between the inner cylindrical member 254 and the 1 housing 252 defines a second flow region that 2 communicates with the production wing branch 202.

4 The upper portion of the secondary conduit 250 is 5 solid (not shown in the cross-sectional view of Fig 6 15) and connects the inner member 254 to the housing 7 252; the solid upper portion has a series of bores 8 therethrough in its outer circumference, which 9 provides a continuation of the annulus 258. The 10 inner member 254 comprises two portions, for ease of 11 manufacture, which are screwed together before the 12 secondary conduit 250 is connected to the choke body 13 204.

15 The inner member 254 is longer than the housing 252, 16 and extends into the choke body 204 to a point below 17 the production wing branch 202. The end of the l8 inner member 254 is provided with a seal 259, which 19 seals in the choke body 204 to prevent direct flow 20 between the first and second flow regions. The 21 secondary conduit 250 is clamped to the choke body 22 204 by a clamp 262 (see Fig 12) that is typically 23 the same clamp as would normally clamp the choke in 24 the choke body 204. The clamp 262 is operable by an 25 ROV.

27 Also shown in Fig 15 is a detailed view of the 28 piping interface 240; the Fig 15 view shows the 29 piping interface 240 before connection with the 30 secondary conduit 250. The piping interface 31 comprises a housing 242 in which is supported an 32 inner member 244. The inner member has a 1 cylindrical bore 246, an upper end of which is in 2 communication with the flexible conduit 238. An 3 annulus 248 is defined between the housing 242 and 4 the inner member 244, the upper end of which is connected to the flexible conduit 236. The piping 6 interface 240 and the secondary conduit 250 have co-7 operating engaging surfaces; in particular the inner 8 member 254 of the secondary conduit 250 is shaped to 9 stab inside the inner member 244 of the piping IO interface 240. The outer surfaces of the housings 11 242, 252 are adapted to receive a clamp 260, which 12 clamps these surfaces together.

14 The piping interface 240 is shown connected to the secondary conduit 250 in the views of Figs 11 and 16 12. As shown in Fig 12, the inner member 254 of the 17 secondary conduit 250 is stabbed inside the inner 18 member 244 of the piping interface 240, and the 19 clamp 260 clamps the housings 242, 252 together.
The cylindrical bores 256, 246 are therefore 21 connected together, as are the annuli 248, 258.
22 Therefore, the cylindrical bores 256 and 24~ form a 23 first flowpath which connects the flexible conduit 24 238 to the production wing outlet 206, and the annuli 248 and 258 form a second flowpath which 26 connects the production wing branch 202 to the 27 flexible conduit 236.

29 A method of connecting the pump 234 to the choke body 204 will now be described with reference to Fig 31 14.

1 Fig 14A shows the tree 200 before connection of the 2 pump 234, with a choke C installed in the choke body 3 204.

The production wing valve is closed and the choke C
6 is removed, as shown in Fig 14B, to allow access to 7 the interior of the choke body 204. This is 8 typically done using conventional choke change out 9 tooling (not shown).
11 Fig 14C shows the secondary conduit 250 being 12 lowered onto the choke body 204. This can also be 13 done using the same choke change out tooling. The 14 secondary conduit 250 is clamped onto the choke body 204 by an ROV operating clamp 262.

17 Fig 14D shows the secondary conduit 250 having 18 landed on and engaged with the choke body 204, and 19 the piping interface 240 being subsequently lowered to connect to the piping interface 240. Fig 15 21 shows a magnified version of Fig 14D for greater 22 clarity.

24 The landing stage of Fig 14D comprises a two-stage process. Tn the first stage, the frame~,220 carrying 26 the pump 234 is landed on the tree 200. The guide 27 funnels 230 of the frame receive the guide legs 210 28 of the tree 200 to provide a first, relatively 29 coarse alignment. The John Brown legs 232 of the frame engage the John Brown feet 208 of the tree 200 32 to provide a more precise alignment.
1 In the second stage, the piping interface 240 is 2 brought into engagement with the secondary conduit 3 250 and the clamp 260 is applied to fix the 4 connection. The two-stage connection process provides protection of the mating surfaces of the 6 secondary conduit 250 and the piping interface 240, 7 and it also protects the choke 204; particularly the 8 mating surface of the choke 204. Instead of landing 9 the frame and connecting the piping interface 240 and secondary conduit in a single movement, which 11 could damage the connection between the piping 12 interface 240 and the secondary conduit 250 and 13 which could also damage the choke 204, the two-stage 14 connection facilitates a controlled, buffered connection.

17 The piping interface 240 being suspended on the 18 curved flexible conduits 236, 238 allows the piping 19 interface 240 to moue in all three spatial dimensions; hence the flexible conduits 236, 238 21 provide a resilient suspension for the piping 22 interface on the pump 234. If the piping interface 23 240 is not initially accurately aligned with the 24 secondary conduit 250, the resilience of the flexible conduits 236, 238 allows the piping 26 interface 240 to deflect laterally, instead of 27 damaging the mating surfaces of the piping interface 28 240 and the secondary conduit 250. Hence, the 29 flexible conduits 236, 238 provide a buffering means to protect the mating surfaces.
1 A slightly modified version of the third embodiment 2 is shown in Fig 16.
The piping interface 240, the 3 secondary conduit 250 and the tree 200 are exactly 4 the same as the Fig embodiment, and like parts are desig nated by like numbers. The piping 6 interface 240 and the secondary conduit are 7 installed on the tree as described for the Fig 11 8 embodiment.

However, in contrast with the Fig 15 embodiment, the 11 Fig 16 embodiment comprises a frame 320 that does 12 not carry a pump. Instead, the frame 320 is 13 provided with two flow hubs 322 (only one shown) 14 that are connected to respective jumpers leading to a processing apparatus remote from the tree. This 16 connection is typically done as a final step, after 17 the frame has landed on the tree and the connection 18 between the piping interface 240 and the secondary 19 conduit 250 has been made up. The processing apparatus could be a pump installed on a further 21 subsea structure, for example a suction pile. A
22 replacement choke 324 is also provided on the frame, 23 which replaces the choke that has been removed from 24 the choke body 204 to allow for insertion of the inner member 254 of the secondary conduit 250 into 26 the choke body 204.

28 The replacement choke 324 is connected to one of the 29 hubs 322 and to one of the flexible conduits 236, 238. The other of the flexible conduits 236, 238 is 32 connected to the other hub 322.

1 The Fig 16 frame is provided with a guide pipe 324 2 that extends perpendicularly to the plane of the 3 frame 320. The guide pipe 324 has a hollow bore and 4 extends downwards from the frame 320, surrounding 5 the piping interface 240 and the vertical portion of 6 at least one (and optionally both) of the flexible 7 conduits 236, 238; the guide pipe 324 has a lateral 8 aperture to allow the conduits 236, 238 to enter the 9 bore. The guide pipe 324 thus provides a guide for 10 the piping interface 240 which protects it from 11 damage from accidental impact with the tree 200, 12 since if the frame 320 is misaligned, the guide pipe 13 324 with impact the tree frame, instead of the 14 piping interface 240. In an alternative embodiment, 15 the guide pipe 324 could be replaced by guide 16 members such as the guide funnels and John Brown 17 legs of the Fig 11 embodiment. In further 18 embodiments, both the guide pipe 324 and these 19 further guide members may be provided.
21 Tn use, the well fluids flow through the choke body 22 240, through the annuli 258, 248, through flexible 23 conduit 238 into one of the hubs 322, through a 24 first jumper conduit, through the processing apparatus (e. g. a pump) through a second jumper 26 conduit, through the other of the hubs 322, through 27 the replacement choke 324, through the flexible 28 conduit 236 through the bores 246, 256 and to the 29 production wing outlet 206. Alternatively, the flow direction could ~be reversed to inject fluids into 31 the well.

1 A further alternative embodiment is shown in Fig 27.
2 This embodiment is very similar to the Fig 16 3 embodiment, and like parts are designated with like 4 numbers. In the Fig 17 embodiment, the second hub 322 is also shown. In this embodiment, the guide 6 pipe 324 surrounds only the flexible conduit 238, 7 the other flexible conduit 236 only entering the 8 guide pipe at the connection to the piping interface 9 240.
l0 l1 The principal difference between the embodiments of 12 Figs 17 and 16 is the provision of an actuating 13 means, which connects the flexible conduit 238 to 14 the frame to control the movement of the flexible conduit 238 and hence the position of the piping 16 interface 240. The actuating means has the form of I7 a hydraulic cylinder, more specifically, a swivel 18 eye mounting hydraulic cylinder 326. The hydraulic 19 cylinder 326 comprises two spherical joints, which allow the lower end of the hydraulic cylinder to 21 swing in a plane parallel to the plane of the frame 22 320 (the X-Y plane of Fig 17). The spherical joints 23 typically comprise spherical eye bushes. The swivel 24 joints typically allow rotation of the hydraulic cylinder around its longitudinal axis by a total of 2~ approximately 180 degrees. The swivel joints also 27 typically allow a swing of plus or minus ten degrees 28 in both the X and Y directions. Hence, the 29. hydraulic cylinder 326 does not fix the position of the flexible conduit 238 rigidly with respect to the 31 frame 320, and does not impede the flexible conduit 1 238 from allowing the piping interface 240 to move 2 in all three dimensions.

4 Fig 17A shows the hydraulic cylinder 236 in a retracted position for landing the frame 320 on the 6 tree 200 or for removing the frame 320 from the tree 7 200. In this retracted position, the flexible 8 conduit 238 holds the piping interface 240 above the 9 secondary conduit 250 so that it cannot engage or impact with the secondary 250' during landing.

12 To make up the connection between the piping 13 interface 240 and the secondary conduit 250, the 14 hydraulic cylinder is extended the extended position is shown in Fig 17B. In the extended 16 position, the piping interface 240 now engages the 17 secondary conduit 250. The pressure in the 18 hydraulic cylinder 326 is now released to allow the 19 clamp 260 to be actuated. The clamp 260 is actuated by an ROV, and pulls the piping interface 240 into 21 even closer contact with the secondary conduit 250 22 to hold these components firmly together.

24 This invention has significant advantages. In the first embodiment, the lower frame member and mandrel 26 are much lighter in weight and less bulky than the 27 upper frame member and pump assembly. Consequently, 28 it is easier to guide the mandrel into engagement 29 with the choke body than it would be if the entire assembly were joined together and lowered as one 31 unit. Once the lower frame member is installed, the 32 upper frame member and pump assembly can be lowered 1 with a lesser chance of damage to the subsea 2 equipment. The upper end of the mandrel is rugged 3 and strong enough to withstand accidental impact by 4 the upper frame member. The two-step process thus makes installation much easier. The optional guide 6 members further provide fine alignment to avoid 7 damage to seating surfaces.

9 The movable upper and lower frame members of the mounting system of the second embodiment avoid 11 damage to the seating surfaces of the mandrel and 12 the receptacle.

14 While the invention has been shown in only a few of its forms, it should be apparent to those skilled in 16 the art that it is not so limited but is susceptible 17 to various changes without departing from the scope 18 of the invention. For example, although shown in 19 connection with a subsea tree assembly, the mounting apparatus could be installed on other subsea 21 structures, such as a manifold or gathering 22 assembly. Also, the flow interface device mounted 23 to the upper frame member could be a compressor for 24 compressing gas, a flow meter for measuring the flow rate of the subsea well, or some other device.

27 In the third embodiment, protection of the 28 connection between the piping interface 240 and the 29 secondary conduit 250 is achieved by the two-step connection process. Additional buffering is 31 provided by the flexible conduits 236, 238, which 32 allow resilient support ~f the piping interface 240 1 relative to the pump/the frame, allowing the piping 2 interface 240 to move in all three dimensions. In 3 some embodiments, even greater control and buffering 4 are achieved using an actuation means to more precisely control the location of the piping 6 interface 240 and its connection with the secondary 7 conduit 250.

9 Improvements and modifications can be incorporated without departing from the scope of the invention.
11 For example, it should be noted that the arrangement 12 of the flowpaths in Figs 11 to 17 are just one 13 example configuration and that alternative 14 arrangements could be made. For example, in Fig 16, 15' the replacement choke could be located in the 16 flowpaths before the first flow hub, so that the 17 fluids pass through the choke before being diverted 18 to the remote processing apparatus. The replacement 19 choke could be located at any suitable point in the flowpaths.

22 Furthermore, in all embodiments, the flowpaths may 23 be reversed, to allow both recovery and injection of 24 fluids. In the third embodiment, the flow directions in the flexible conduits 236, 238 (and in 26 the rest of the apparatus) would be reversed.

28 A replacement choke 324 could also be used in the 29 other embodiments, as described for the Fig 16 embodiment. The replacement choke 234 need not be 31 provided on the frame.

1 All embodiments of the invention could be provided 2 with a guide pipe, such as that shown in Fig 16.

4 In alternative embodiments, the actuating means of 5 Fig 17 is not necessarily a swivel eye mounting 6 hydraulic cylinder 326. In other embodiments, the 7 hydraulic cylinder may only have a single swivelable 8 connection, and in other embodiments, the hydraulic 9 cylinder could have a reduced or even almost no 10 range of movement in the X-Y plane. In further 11 embodiments, this hydraulsc cylinder could be 12 replaced by a simple cable in the form of a string, 13 which is attached to a part of the flexible conduit 14 238. The flexible conduit 238 could then simply be 15 raised and lowered as desired by pulling and 16 releasing the tension in the cable. In a further 17 embodiment, the hydraulic cylinder could be replaced 18 by a screw jack, also known as a power jack, a first 19 screw member of the screw jack being attached to the 20 frame, and a second screw member being coupled to 21 the flexible conduit 238. Operating the screw jack 22 also raises and lowers the end of the conduit means, 23 as desired.

25 Although the above disclosures principally refer to 26 the production wing branch and the production choke, 27 the invention could equally be applied to a choke 28 body of the annulus wing branch.

30 In the Fig 11 embodiment, either of the conduits 31 236, 238 could be attached to the inlet and the 32 outlet of the pump 234 and either may be attached to l the inlet and the outlet of the piping interface 2 240.

4 Many different types of processing apparatus could be used. Typically, the processing apparatus 6 comprises at least one of: a pump; a process fluid 7 turbine; injection apparatus; chemical injection 8 apparatus; a fluid riser; measurement apparatus;
9 temperature measurement apparatus; flow rate measurement apparatus; constitution measurement 11 apparatus; consistency measurement apparatus; gas 12 separation apparatus; water separation apparatus;
13 solids separation apparat us; and hydrocarbon 14 separation apparatus.
16 The processing apparatus could comprise a pump or 17 process fluid turbine, for boosting the pressure of 18 the fluid. Alternatively, or additionally, the 19 processing apparatus could inject gas, steam, sea water, drill cuttings or waste material into the 21 fluids. The injection of gas could be advantageous, 22 as it would give the fluids "lift", making them 23 easier to pump. The addition of steam has the 24 effect of adding energy to the fluids.
26 Injecting sea water into a well could be useful to 27 boost the formation pressure for recovery of 28 hydrocarbons from the well, and to maintain the 29 pressure in the underground formation against collapse. Also, injecting waste gases or drill 31 cuttings etc into a well obviates the need to 2 dispose of these at the surface, which can prove 2 expensive and environmentally damaging.

4 The processing apparatus could also enable chemicals to be added to the fluids, e.g. viscosity 6 moderators, which thin out the fluids, making them 7 easier to pump, or pipe skin friction moderators, 8 which minimise the friction between the fluids and 9 the pipes. Further examples of chemicals which could be injected are surfactants, refrigerants, and 11 well fracturing chemicals. The processing apparatus 12 could also comprise injection water electrolysis 13 equipment.

The processing apparatus could also comprise a fluid 26 riser, which could provide an alternative route 17 between the well bore and the surface. This could 18 lae very useful if, for example, the flowline 206 19 becomes blocked.
21 Alternatively, processing apparatus could comprise 22 separation equipment e.g. for separating gas, water, 23 sand/debris and/or hydrocarbons. The separated 24 components) could be siphoned off via one or more additional process conduits.

27 The processing apparatus could alternatively or 28 additionally include measurement apparatus, e.g. for 29 measuring the temperature/ flow rate/ constitution/
consistency, etc. The temperature could then be 31 compared to temperature readings taken from the 32 bottom of the well to calculate the temperature 1 change in produced fluids. Furthermore, the 2 processing apparatus could include injection water 3 electrolysis equipment.

Claims (41)

Claims
1. An apparatus for connecting to a subsea wellbore, the wellbore comprising a manifold and a choke body, the apparatus comprising:

a frame adapted to land on the manifold;

a conduit system comprising a first end for connection to the choke body and a second end for connection to a processing apparatus;

wherein the conduit system comprises a conduit means supported by the frame;
wherein the frame comprises at least one frame member that is adapted to land on the manifold in a first stage of the connection; and wherein the conduit means is adapted to be brought into fluid communication with the choke body in a second stage of the connection.
2. The apparatus as claimed in claim 1, further comprising an actuating means mounted on the frame, the actuating means being adapted to bring the conduit means into fluid communication with the choke body.
3. The apparatus as claimed in claim 1, wherein the conduit means comprises a flexible conduit.
4. The apparatus as claimed in claim 3, wherein the flexible conduit is arranged to buffer the connection of the conduit means and the choke body.
5. The apparatus as claimed in claim 3, wherein the flexible conduit comprises an end that is fixed relative to the frame and an opposite end that is moveable relative to the frame.
6. The apparatus as claimed in claim 2, wherein the conduit means comprises a flexible conduit, and wherein the actuating means is adapted to move a movable end of the flexible conduit relative to the frame to bring it into fluid communication with the choke body.
7. The apparatus as claimed in claim 6, wherein the actuation means comprises at least one swivel device that allows movement of the moveable end of the flexible conduit in more than one dimension.
8. The apparatus as claimed in claim 3, wherein the flexible conduit is resilient.
9. The apparatus as claimed in claim 8, wherein the flexible conduit is curved to provide resilience wherein the direction of movement of the flexible conduit in the second stage of the connection defines an axis of connection and wherein the curvature is in a plane perpendicular to the axis of connection to provide resilience in the connection direction.
10. The apparatus as claimed in claim 3, wherein the conduit means comprises two flexible conduits wherein each of the two conduits is fixed at a respective end thereof relative to the frame and wherein each of the two conduits has a respective opposite end that is moveable relative to the frame.
11. The apparatus as claimed in claim 1, wherein the conduit system further comprises a secondary conduit that is connected to the interior of the choke body and wherein the conduit means is adapted to connect to the secondary conduit in the second stage of the connection to connect the conduit means to the choke body via the secondary conduit.
12. The apparatus as claimed in claim 2, wherein the frame comprises a lower frame member and an upper frame member, the conduit means being mounted on the upper frame member, and wherein the actuating means is mounted between the lower and upper frame members and is adapted to move the upper frame member relative to the lower frame member to bring the conduit means into fluid communication with the choke body.
13. The apparatus as claimed in claim 12, wherein the actuating means is adapted to buffer the connection between the conduit means and the choke body.
14. The apparatus as claimed in claim 1, wherein the at least one frame member of the first connection stage comprises a lower frame member, and wherein the apparatus further comprises an upper frame member, the upper frame member and the lower frame member having co-operating engagement means for landing the upper frame member on the lower frame member.
15. The apparatus as claimed in claim 14, further comprising buffering means provided on the frame, the buffering means defining a minimum distance between the frame and the manifold.
16. The apparatus as claimed in claim 1, wherein the conduit system provides a single flowpath between the choke body and the processing apparatus.
17. The apparatus as claimed in claim 1, wherein the conduit system provides a first flowpath from the choke body to the processing apparatus and a second flowpath from the processing apparatus to the choke body.
18. The apparatus as claimed in claim 17, wherein the conduit system comprises a housing and an inner hollow cylindrical member, the inner cylindrical member being adapted to seal within the choke body to define a first flow region through the bore of the cylindrical member and a second separate flow region in the annulus between the cylindrical member and the housing.
19. The apparatus as claimed in claim 18, wherein the first and second flow regions are adapted to connect to a respective inlet and an outlet of the processing apparatus.
20. The apparatus as claimed in claim 1 wherein the processing apparatus is provided on the frame.
21. The apparatus as claimed in claim 1, wherein the processing apparatus is provided on a separate subsea structure.
22. The apparatus as claimed in claim 1, wherein a replacement choke is provided on the frame, the replacement choke being connectable to the conduit system.
23. A method of connecting a processing apparatus to a subsea wellbore, the wellbore comprising a manifold and the manifold comprising a choke body, the method comprising:
landing a frame on the manifold and connecting a conduit system between the choke body and the processing apparatus, the frame supporting a conduit means of the conduit system;

wherein the frame comprises at least one frame member that is landed on the manifold in a first connection stage, and wherein the conduit means is brought into fluid communication with the choke body in a second connection stage.
24. The method as claimed in claim 23, wherein actuating means are mounted on the frame, and wherein the method includes actuating the actuating means to bring the conduit means into fluid communication with the choke body.
25. The method as claimed in claim 24, wherein the conduit means comprises a flexible conduit, one end of which is moveable relative to the frame, and wherein the method includes actuating the actuating means to move the moveable end of the flexible conduit portion relative to the frame to bring it into fluid communication with the choke body.
26. The method as claimed in claim 23, wherein the conduit system further comprises a secondary conduit that is connected to the choke body and wherein the method includes connecting the conduit means to the secondary conduit in the second stage of the connection.
27. The method as claimed in claim 24, wherein the frame comprises a lower frame member and an upper frame member, the conduit means being supported on the upper frame member, wherein the actuating means is mounted between the lower and upper frame members, and wherein the method includes actuating the actuation means to move the upper frame member relative to the lower frame member to bring the conduit means into fluid communication with the choke body.
28. The method as claimed in claim 23, wherein the at least one frame member of the first connection stage comprises a lower frame member, and wherein the apparatus further comprises an upper frame member, and wherein the method includes the upper frame member on the lower frame member.
29. The method as claimed in claim 23, further including buffering the connection between the choke body and the conduit means.
30. The method as claimed in claim 26, wherein the method includes removing a choke bonnet and connecting the secondary conduit to the interior of the choke body.
31. The method as claimed in claim 23, wherein the conduit system provides a first flowpath from the choke body to the processing apparatus and a second flowpath from the processing apparatus to the choke body and wherein the method includes connecting the first and second flowpaths to a respective inlet and an outlet of the processing apparatus.
32. The method as claimed in claim 23, wherein the method includes connecting a replacement choke with the conduit system so that fluids flowing through the conduit system also flow through the replacement choke.
33. An apparatus for landing on and connecting to a subsea tree, comprising a choke body, the apparatus comprising:

a frame comprising a conduit system, the frame being adapted to land on the tree, the conduit system including a conduit having a first end which is adapted to connect to the choke body such that the conduit is in fluid communication with the interior of the choke body, and a second end connectable to a processing apparatus;

wherein the frame comprises buffering means adapted to buffer the connection between the first end of the conduit system and the choke body.
34. An apparatus for connecting to a subsea wellbore, the wellbore comprising a manifold and a choke body, the apparatus comprising:

a frame adapted to land on the manifold;

a conduit system comprising at least one flexible conduit having a first downwards facing end for connection to an upper face of the choke body and a second end for connection to a processing apparatus;

wherein at least a part of the conduit system is supported by the frame;
wherein the flexible conduit comprises a semicircular coil from which the downwards facing end is suspended and wherein the flexibility of the semicircular coil allows the downwards facing end to be moveable relative to the frame to make up a communication between the processing apparatus and the choke body.
35. A subsea assembly comprising:

a subsea manifold comprising a choke body; and a connection apparatus for connecting to the subsea manifold;
wherein the connection apparatus comprises:

a frame adapted to land on the manifold;

a conduit system comprising a first end adapted to connect to the choke body and a second end adapted to connect to a processing apparatus;
wherein the conduit system comprises a conduit means supported by the frame; and wherein the frame comprises at least one frame member that is adapted to land on the manifold in a first stage of the connection and wherein the conduit means is adapted to be brought into fluid communication with the choke body of the manifold in a second stage of the connection.
36. An apparatus for landing on and connecting to a subsea tree that includes a choke body with a bore in communication with a production bore of the tree forming a first flowpath, the apparatus including:

a frame landable on and supportable by the tree;

a processing apparatus supportable by the frame; and a conduit system forming a second flowpath that allows fluid communication from the tree production bore, through the processing apparatus, and into the choke body bore.
37. The apparatus of claim 36, where the tree further includes a lateral production port in communication with the production bore, the apparatus further including the conduit system allowing fluid communication between the processing apparatus and the lateral production port.
38. The apparatus of claim 36, where the conduit system allows fluid to be diverted from the first flowpath to the second flowpath.
39. A production tree including:

a tree body including a production bore and a lateral production port extending from the bore into a wing block in a first flowpath; and a utility skid landable on and supportable by the tree, the skid including:
a frame;

a processing apparatus supportable by the frame; and a conduit system that allows fluid communication in a second flowpath between the production bore, the processing apparatus, and the lateral production port.
40. The production tree of claim 39, further including a choke body attached to the tree wing block and including a bore, the conduit system allowing fluid communication between the choke body bore and the processing apparatus.
41. The production tree of claim 39, where the conduit system allows fluid to be diverted from the first flowpath to the second flowpath.
CA2555403A 2004-02-26 2005-02-25 Connection system for subsea flow interface equipment Active CA2555403C (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
US54872704P 2004-02-26 2004-02-26
US60/548,727 2004-02-26
PCT/GB2005/000725 WO2005083228A1 (en) 2004-02-26 2005-02-25 Connection system for subsea flow interface equipment

Publications (2)

Publication Number Publication Date
CA2555403A1 CA2555403A1 (en) 2005-09-09
CA2555403C true CA2555403C (en) 2012-08-21

Family

ID=34911011

Family Applications (1)

Application Number Title Priority Date Filing Date
CA2555403A Active CA2555403C (en) 2004-02-26 2005-02-25 Connection system for subsea flow interface equipment

Country Status (9)

Country Link
US (5) US8066076B2 (en)
EP (1) EP1721058B1 (en)
AT (1) ATE426730T1 (en)
AU (1) AU2005216412B2 (en)
BR (1) BRPI0508049B8 (en)
CA (1) CA2555403C (en)
DE (1) DE602005013496D1 (en)
NO (1) NO337264B1 (en)
WO (1) WO2005083228A1 (en)

Families Citing this family (54)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP1990505B1 (en) 2003-05-31 2010-09-22 Cameron Systems (Ireland) Limited Apparatus and method for recovering fluids from a well and/or injecting fluids into a well
DE602005013496D1 (en) * 2004-02-26 2009-05-07 Cameron Systems Ireland Ltd CONNECTION SYSTEM FOR UNDERWATER FLOW SURFACE EQUIPMENT
US7686086B2 (en) * 2005-12-08 2010-03-30 Vetco Gray Inc. Subsea well separation and reinjection system
US8579033B1 (en) * 2006-05-08 2013-11-12 Mako Rentals, Inc. Rotating and reciprocating swivel apparatus and method with threaded end caps
GB0618001D0 (en) 2006-09-13 2006-10-18 Des Enhanced Recovery Ltd Method
GB0625191D0 (en) 2006-12-18 2007-01-24 Des Enhanced Recovery Ltd Apparatus and method
GB0625526D0 (en) * 2006-12-18 2007-01-31 Des Enhanced Recovery Ltd Apparatus and method
EP2111496B1 (en) 2007-02-01 2018-07-25 Cameron International Corporation Chemical-injection management system
BRPI0812880A2 (en) * 2007-06-01 2014-12-09 Agr Deepwater Dev Systems Inc SYSTEM AND METHOD FOR LIFTING A WELL HOLE DRILLING FLUID IN A TRAINING, PITCHING LIFTING RETURN FLUID SYSTEM IN A TRAINING, METHOD FOR CONTROLING A WELL HOLE IN A FORMATION
EP2383425A3 (en) * 2007-09-26 2014-03-12 Cameron International Corporation Choke assembly
GB2454807B (en) * 2007-11-19 2012-04-18 Vetco Gray Inc Utility skid tree support system for subsea wellhead
NO328942B1 (en) * 2008-05-15 2010-06-21 Aker Subsea As Manifold structure with adjustable brackets
US8151890B2 (en) * 2008-10-27 2012-04-10 Vetco Gray Inc. System, method and apparatus for a modular production tree assembly to reduce weight during transfer of tree to rig
MX2011004404A (en) * 2008-12-05 2011-06-16 Cameron Internac Corp Sub-sea chemical injection metering valve.
WO2010129178A2 (en) 2009-05-04 2010-11-11 Cameron International Corporation System and method of providing high pressure fluid injection with metering using low pressure supply lines
NO339428B1 (en) * 2009-05-25 2016-12-12 Roxar Flow Measurement As Valve
GB2486123B (en) * 2009-09-25 2013-09-11 Aker Subsea As Production manifold accessory
US8672038B2 (en) * 2010-02-10 2014-03-18 Magnum Subsea Systems Pte Ltd. Retrievable subsea bridge tree assembly and method
NO332503B1 (en) * 2010-11-18 2012-10-01 Aker Subsea As Guidepost extension
US8522624B2 (en) 2011-03-02 2013-09-03 Cameron International Corporation System and method for pressure balancing a flow meter
CA2837692A1 (en) * 2011-06-17 2012-12-20 Bp Corporation North America Inc. Air-freightable containment cap for containing a subsea well
US20130000918A1 (en) * 2011-06-29 2013-01-03 Vetco Gray Inc. Flow module placement between a subsea tree and a tubing hanger spool
US10307167B2 (en) 2012-12-14 2019-06-04 Corquest Medical, Inc. Assembly and method for left atrial appendage occlusion
US10314594B2 (en) 2012-12-14 2019-06-11 Corquest Medical, Inc. Assembly and method for left atrial appendage occlusion
US10813630B2 (en) 2011-08-09 2020-10-27 Corquest Medical, Inc. Closure system for atrial wall
SG11201403959PA (en) * 2012-02-09 2014-10-30 Cameron Int Corp Retrievable flow module unit
GB201202581D0 (en) * 2012-02-15 2012-03-28 Dashstream Ltd Method and apparatus for oil and gas operations
US9702220B2 (en) 2012-02-21 2017-07-11 Onesubsea Ip Uk Limited Well tree hub and interface for retrievable processing modules
MY165077A (en) 2012-04-26 2018-02-28 Ian Donald Oilfield apparatus and methods of use
MY164630A (en) 2012-04-26 2018-01-30 Ian Donald Oilfield apparatus and methods of use
US9169709B2 (en) * 2012-11-01 2015-10-27 Onesubsea Ip Uk Limited Spool module
US20140142689A1 (en) 2012-11-21 2014-05-22 Didier De Canniere Device and method of treating heart valve malfunction
GB2514150B (en) * 2013-05-15 2016-05-18 Aker Subsea Ltd Subsea connections
US9365271B2 (en) 2013-09-10 2016-06-14 Cameron International Corporation Fluid injection system
US9566443B2 (en) 2013-11-26 2017-02-14 Corquest Medical, Inc. System for treating heart valve malfunction including mitral regurgitation
GB2540300B (en) 2014-04-24 2019-01-09 Onesubsea Ip Uk Ltd Self-regulating flow control device
US10842626B2 (en) 2014-12-09 2020-11-24 Didier De Canniere Intracardiac device to correct mitral regurgitation
EP3789581B1 (en) 2014-12-15 2022-04-06 Enpro Subsea Limited Apparatus, systems and methods for oil and gas operations
GB201506266D0 (en) 2015-04-13 2015-05-27 Enpro Subsea Ltd Apparatus, systems and methods for oil and gas operations
US10711597B2 (en) 2015-06-22 2020-07-14 Baker Hughes, A Ge Company, Llc Power transmission and communication between processors and energy industry devices
EP3369909B1 (en) * 2015-12-04 2021-10-27 Mitsubishi Heavy Industries Engine & Turbocharger, Ltd. Turbocharger, engine system, and control method for turbocharger
SG11201804748PA (en) 2016-02-03 2018-08-30 Fmc Technologies Systems for removing blockages in subsea flowlines and equipment
US9702215B1 (en) * 2016-02-29 2017-07-11 Fmc Technologies, Inc. Subsea tree and methods of using the same
EP3436657B1 (en) * 2016-03-30 2021-03-10 Oceaneering International, Inc. Compact distributed subsea distribution of hydraulic power and chemical injection
GB2551953B (en) * 2016-04-11 2021-10-13 Equinor Energy As Tie in of pipeline to subsea structure
DE102016006068A1 (en) * 2016-05-19 2017-11-23 Scotland Gas Networks Plc Long-shaft tool, system of a long-tool with a first manipulator and a second manipulator and use for such a tool and such a system
NO344601B1 (en) * 2016-10-31 2020-02-10 Bri Cleanup As Assembly for an oil and gas production platform or rig, and related methods
US20180154498A1 (en) * 2016-12-05 2018-06-07 Onesubsea Ip Uk Limited Burnishing assembly systems and methods
GB201803680D0 (en) 2018-03-07 2018-04-25 Enpro Subsea Ltd Apparatus, systems and methods for oil and gas operations
US10478753B1 (en) 2018-12-20 2019-11-19 CH International Equipment Ltd. Apparatus and method for treatment of hydraulic fracturing fluid during hydraulic fracturing
BR112021012087A2 (en) 2018-12-20 2021-08-31 Haven Technology Solutions Llc TWO PHASE FLOW SEPARATOR SYSTEM, AND METHOD FOR SEPARATING A TWO PHASE CONTINUOUS FLOW FLOW
BR112021026605A2 (en) 2019-07-01 2022-05-10 Onesubsea Ip Uk Ltd Flow measurement and monitoring device for an underwater tree
US11230907B2 (en) * 2019-07-23 2022-01-25 Onesubsea Ip Uk Limited Horizontal connector system and method
US11371295B2 (en) * 2020-04-16 2022-06-28 Dril-Quip, Inc. Wellhead connector soft landing system and method

Family Cites Families (239)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB242913A (en) 1925-06-25 1925-11-19 Albert Wainman Improvements in convertible settees
US1758376A (en) * 1926-01-09 1930-05-13 Nelson E Reynolds Method and means to pump oil with fluids
US1994840A (en) * 1930-05-27 1935-03-19 Caterpillar Tractor Co Chain
US1944573A (en) * 1931-10-12 1934-01-23 William A Raymond Control head
US1944840A (en) * 1933-02-24 1934-01-23 Margia Manning Control head for wells
US2132199A (en) * 1936-10-12 1938-10-04 Gray Tool Co Well head installation with choke valve
US2276883A (en) * 1937-05-18 1942-03-17 Standard Catalytic Co Apparatus for preheating liquid carbonaceous material
US2233077A (en) * 1938-10-10 1941-02-25 Barker Well controlling apparatus
US2412765A (en) * 1941-07-25 1946-12-17 Phillips Petroleum Co Recovery of hydrocarbons
US2962356A (en) * 1953-09-09 1960-11-29 Monsanto Chemicals Corrosion inhibition
US2790500A (en) * 1954-03-24 1957-04-30 Edward N Jones Pump for propelling pellets into oil wells for treating the same
US2893435A (en) * 1956-02-03 1959-07-07 Mcevoy Co Choke
US3101118A (en) * 1959-08-17 1963-08-20 Shell Oil Co Y-branched wellhead assembly
GB1022352A (en) 1961-06-25 1966-03-09 Ass Elect Ind Improvements relating to intercoolers for rotary gas compressors
US3163224A (en) * 1962-04-20 1964-12-29 Shell Oil Co Underwater well drilling apparatus
US3378066A (en) * 1965-09-30 1968-04-16 Shell Oil Co Underwater wellhead connection
US3358753A (en) * 1965-12-30 1967-12-19 Shell Oil Co Underwater flowline installation
FR1567019A (en) 1967-01-19 1969-05-16
US3608631A (en) * 1967-11-14 1971-09-28 Otis Eng Co Apparatus for pumping tools into and out of a well
US3593808A (en) * 1969-01-07 1971-07-20 Arthur J Nelson Apparatus and method for drilling underwater
US3603409A (en) * 1969-03-27 1971-09-07 Regan Forge & Eng Co Method and apparatus for balancing subsea internal and external well pressures
US3710859A (en) * 1970-05-27 1973-01-16 Vetco Offshore Ind Inc Apparatus for remotely connecting and disconnecting pipe lines to and from a submerged wellhead
US3705626A (en) * 1970-11-19 1972-12-12 Mobil Oil Corp Oil well flow control method
US3688840A (en) * 1971-02-16 1972-09-05 Cameron Iron Works Inc Method and apparatus for use in drilling a well
US3777812A (en) 1971-11-26 1973-12-11 Exxon Production Research Co Subsea production system
FR2165719B1 (en) * 1971-12-27 1974-08-30 Subsea Equipment Ass Ltd
US3753257A (en) 1972-02-28 1973-08-14 Atlantic Richfield Co Well monitoring for production of solids
US3820558A (en) * 1973-01-11 1974-06-28 Rex Chainbelt Inc Combination valve
FR2253976B1 (en) * 1973-12-05 1976-11-19 Subsea Equipment Ass Ltd
US4125345A (en) 1974-09-20 1978-11-14 Hitachi, Ltd. Turbo-fluid device
US3957079A (en) * 1975-01-06 1976-05-18 C. Jim Stewart & Stevenson, Inc. Valve assembly for a subsea well control system
FR2314350A1 (en) * 1975-06-13 1977-01-07 Seal Petroleum Ltd METHOD OF INSTALLATION AND INSPECTION OF A SET OF VALVES OF A SUBMARINE OIL WELL HEAD AND IMPLEMENTATION TOOL
US4046191A (en) * 1975-07-07 1977-09-06 Exxon Production Research Company Subsea hydraulic choke
US4090366A (en) * 1976-05-12 1978-05-23 Vickers-Intertek Limited Transit capsules
US4042033A (en) * 1976-10-01 1977-08-16 Exxon Production Research Company Combination subsurface safety valve and chemical injector valve
US4120362A (en) 1976-11-22 1978-10-17 Societe Nationale Elf Aquitaine (Production) Subsea station
US4095649A (en) 1977-01-13 1978-06-20 Societe Nationale Elf Aquitaine (Production) Reentry system for subsea well apparatus
AU498216B2 (en) 1977-03-21 1979-02-22 Exxon Production Research Co Blowout preventer bypass
US4099583A (en) * 1977-04-11 1978-07-11 Exxon Production Research Company Gas lift system for marine drilling riser
US4105068A (en) 1977-07-29 1978-08-08 Chicago Bridge & Iron Company Apparatus for producing oil and gas offshore
FR2399609A1 (en) * 1977-08-05 1979-03-02 Seal Participants Holdings AUTOMATIC CONNECTION OF TWO DUCTS LIKELY TO PRESENT AN ALIGNMENT DEVIATION
US4102401A (en) 1977-09-06 1978-07-25 Exxon Production Research Company Well treatment fluid diversion with low density ball sealers
US4190120A (en) 1977-11-18 1980-02-26 Regan Offshore International, Inc. Moveable guide structure for a sub-sea drilling template
US4260022A (en) * 1978-09-22 1981-04-07 Vetco, Inc. Through the flow-line selector apparatus and method
US4223728A (en) * 1978-11-30 1980-09-23 Garrett Energy Research & Engineering Inc. Method of oil recovery from underground reservoirs
US4210208A (en) * 1978-12-04 1980-07-01 Sedco, Inc. Subsea choke and riser pressure equalization system
US4294471A (en) * 1979-11-30 1981-10-13 Vetco Inc. Subsea flowline connector
JPS5919883Y2 (en) 1980-03-19 1984-06-08 日立建機株式会社 annular heat exchanger
US4291772A (en) * 1980-03-25 1981-09-29 Standard Oil Company (Indiana) Drilling fluid bypass for marine riser
US4403658A (en) * 1980-09-04 1983-09-13 Hughes Tool Company Multiline riser support and connection system and method for subsea wells
GB2089866B (en) * 1980-12-18 1984-08-30 Mecevoy Oilfield Equipment Co Underwater christmas tree cap and lockdown apparatus
US4347899A (en) * 1980-12-19 1982-09-07 Mobil Oil Corporation Downhold injection of well-treating chemical during production by gas lift
US4401164A (en) * 1981-04-24 1983-08-30 Baugh Benton F In situ method and apparatus for inspecting and repairing subsea wellheads
US4457489A (en) * 1981-07-13 1984-07-03 Gilmore Samuel E Subsea fluid conduit connections for remote controlled valves
US4444275A (en) 1981-12-02 1984-04-24 Standard Oil Company Carousel for vertically moored platform
CH638019A5 (en) 1982-04-08 1983-08-31 Sulzer Ag Compressor system
GB2121458A (en) * 1982-06-05 1983-12-21 British Petroleum Co Plc Oil production system
US4509599A (en) * 1982-10-01 1985-04-09 Baker Oil Tools, Inc. Gas well liquid removal system and process
BR8307599A (en) 1982-11-05 1984-10-02 Hydril Co SAFETY VALVE APPARATUS AND PROCESS
US4502534A (en) * 1982-12-13 1985-03-05 Hydril Company Flow diverter
US4478287A (en) * 1983-01-27 1984-10-23 Hydril Company Well control method and apparatus
US4503878A (en) * 1983-04-29 1985-03-12 Cameron Iron Works, Inc. Choke valve
US4589493A (en) * 1984-04-02 1986-05-20 Cameron Iron Works, Inc. Subsea wellhead production apparatus with a retrievable subsea choke
US4626135A (en) * 1984-10-22 1986-12-02 Hydril Company Marine riser well control method and apparatus
US4607701A (en) * 1984-11-01 1986-08-26 Vetco Offshore Industries, Inc. Tree control manifold
GB8429920D0 (en) 1984-11-27 1985-01-03 Vickers Plc Marine anchors
US4646844A (en) * 1984-12-24 1987-03-03 Hydril Company Diverter/bop system and method for a bottom supported offshore drilling rig
GB8505327D0 (en) * 1985-03-01 1985-04-03 Texaco Ltd Subsea well head template
US4630681A (en) * 1985-02-25 1986-12-23 Decision-Tree Associates, Inc. Multi-well hydrocarbon development system
GB8505328D0 (en) * 1985-03-01 1985-04-03 Texaco Ltd Subsea well head allignment system
US4648629A (en) 1985-05-01 1987-03-10 Vetco Offshore, Inc. Underwater connector
US4629003A (en) * 1985-08-01 1986-12-16 Baugh Benton F Guilelineless subsea completion system with horizontal flowline connection
CA1265992A (en) 1986-01-13 1990-02-20 Yoshiaki Ikuta Method for drawing up special crude oil
US4695190A (en) * 1986-03-04 1987-09-22 Smith International, Inc. Pressure-balanced stab connection
US4749046A (en) 1986-05-28 1988-06-07 Otis Engineering Corporation Well drilling and completion apparatus
JPS634197A (en) 1986-06-25 1988-01-09 三菱重工業株式会社 Method of drilling special crude oil
US4702320A (en) * 1986-07-31 1987-10-27 Otis Engineering Corporation Method and system for attaching and removing equipment from a wellhead
NO175020C (en) * 1986-08-04 1994-08-17 Norske Stats Oljeselskap Method of transporting untreated well stream
GB8623900D0 (en) * 1986-10-04 1986-11-05 British Petroleum Co Plc Subsea oil production system
GB8627489D0 (en) 1986-11-18 1986-12-17 British Petroleum Co Plc Stimulating oil production
US4896725A (en) * 1986-11-25 1990-01-30 Parker Marvin T In-well heat exchange method for improved recovery of subterranean fluids with poor flowability
GB8707307D0 (en) * 1987-03-26 1987-04-29 British Petroleum Co Plc Sea bed process complex
US4813495A (en) * 1987-05-05 1989-03-21 Conoco Inc. Method and apparatus for deepwater drilling
GB2209361A (en) * 1987-09-04 1989-05-10 Autocon Ltd Controlling underwater installations
US4830111A (en) * 1987-09-09 1989-05-16 Jenkins Jerold D Water well treating method
US4820083A (en) * 1987-10-28 1989-04-11 Amoco Corporation Flexible flowline connection to a subsea wellhead assembly
DE3738424A1 (en) 1987-11-12 1989-05-24 Dreier Werk Gmbh Shower cubicle as prefabricated unit
US4848473A (en) * 1987-12-21 1989-07-18 Chevron Research Company Subsea well choke system
US4911240A (en) * 1987-12-28 1990-03-27 Haney Robert C Self treating paraffin removing apparatus and method
US4874008A (en) * 1988-04-20 1989-10-17 Cameron Iron Works U.S.A., Inc. Valve mounting and block manifold
NO890467D0 (en) 1989-02-06 1989-02-06 Sinvent As HYDRAULIC DRIVE Piston Pump for Multiphase Flow Compression.
US4972904A (en) 1989-08-24 1990-11-27 Foster Oilfield Equipment Co. Geothermal well chemical injection system
US4926898A (en) 1989-10-23 1990-05-22 Sampey Ted J Safety choke valve
GB8925075D0 (en) * 1989-11-07 1989-12-28 British Petroleum Co Plc Sub-sea well injection system
US5044672A (en) * 1990-03-22 1991-09-03 Fmc Corporation Metal-to-metal sealing pipe swivel joint
US5010956A (en) 1990-03-28 1991-04-30 Exxon Production Research Company Subsea tree cap well choke system
US5143158A (en) 1990-04-27 1992-09-01 Dril-Quip, Inc. Subsea wellhead apparatus
US5069286A (en) 1990-04-30 1991-12-03 The Mogul Corporation Method for prevention of well fouling
GB9014237D0 (en) 1990-06-26 1990-08-15 Framo Dev Ltd Subsea pump system
BR9005132A (en) * 1990-10-12 1992-04-14 Petroleo Brasileiro Sa SUBMARINE CONNECTION SYSTEM AND ACTIVE CONNECTOR USED IN THIS SYSTEM
US5074519A (en) 1990-11-09 1991-12-24 Cooper Industries, Inc. Fail-close hydraulically actuated control choke
FR2672935B1 (en) * 1991-02-14 1999-02-26 Elf Aquitaine UNDERWATER WELL HEAD.
US5295534A (en) 1991-04-15 1994-03-22 Texaco Inc. Pressure monitoring of a producing well
BR9103428A (en) 1991-08-09 1993-03-09 Petroleo Brasileiro Sa WET CHRISTMAS TREE
BR9103429A (en) * 1991-08-09 1993-03-09 Petroleo Brasileiro Sa SATELLITE TREE MODULE AND STRUCTURE OF FLOW LINES FOR INTERCONNECTING A SATELLITE POCO TO A SUBMARINE PRODUCTION SYSTEM
US5201491A (en) 1992-02-21 1993-04-13 Texaco Inc. Adjustable well choke mechanism
US5248166A (en) * 1992-03-31 1993-09-28 Cooper Industries, Inc. Flowline safety joint
EP0568742A1 (en) 1992-05-08 1993-11-10 Cooper Industries, Inc. Transfer of production fluid from a well
JPH05310613A (en) 1992-05-12 1993-11-22 Mitsubishi Gas Chem Co Inc Production of monoalkenylbenzene
DE989283T1 (en) 1992-06-01 2001-03-01 Cooper Cameron Corp Wellhead
GB2267920B (en) 1992-06-17 1995-12-06 Petroleum Eng Services Improvements in or relating to well-head structures
US5255745A (en) * 1992-06-18 1993-10-26 Cooper Industries, Inc. Remotely operable horizontal connection apparatus and method
US5377762A (en) 1993-02-09 1995-01-03 Cooper Industries, Inc. Bore selector
US5398761A (en) 1993-05-03 1995-03-21 Syntron, Inc. Subsea blowout preventer modular control pod
GB9311583D0 (en) * 1993-06-04 1993-07-21 Cooper Ind Inc Modular control system
JPH0783266A (en) 1993-09-14 1995-03-28 Nippon Seiko Kk Electric viscous fluid damper for slide mechanism
FR2710946B1 (en) 1993-10-06 2001-06-15 Inst Francais Du Petrole Energy generation and transfer system.
GB2282863B (en) 1993-10-14 1997-06-18 Vinten Group Plc Improvements in or relating to apparatus mountings providing at least one axis of movement with damping
US5492436A (en) 1994-04-14 1996-02-20 Pool Company Apparatus and method for moving rig structures
NO309442B1 (en) * 1994-05-06 2001-01-29 Abb Offshore Systems As System and method for withdrawal and interconnection of two submarine pipelines
US5553514A (en) 1994-06-06 1996-09-10 Stahl International, Inc. Active torsional vibration damper
KR0129664Y1 (en) 1994-06-30 1999-01-15 김광호 Damping device for a robot
GB9418088D0 (en) 1994-09-08 1994-10-26 Exploration & Prod Serv Horizontal subsea tree pressure compensated plug
US5526882A (en) 1995-01-19 1996-06-18 Sonsub, Inc. Subsea drilling and production template system
US5762149A (en) 1995-03-27 1998-06-09 Baker Hughes Incorporated Method and apparatus for well bore construction
GB9514510D0 (en) 1995-07-15 1995-09-13 Expro North Sea Ltd Lightweight intervention system
GB9519454D0 (en) 1995-09-23 1995-11-22 Expro North Sea Ltd Simplified xmas tree using sub-sea test tree
US5730551A (en) * 1995-11-14 1998-03-24 Fmc Corporation Subsea connector system and method for coupling subsea conduits
US5649594A (en) * 1995-12-11 1997-07-22 Boots & Coots, L.P. Method and apparatus for servicing a wellhead assembly
US6457540B2 (en) 1996-02-01 2002-10-01 Robert Gardes Method and system for hydraulic friction controlled drilling and completing geopressured wells utilizing concentric drill strings
NO305179B1 (en) 1996-08-27 1999-04-12 Norske Stats Oljeselskap Underwater well device
US6279658B1 (en) 1996-10-08 2001-08-28 Baker Hughes Incorporated Method of forming and servicing wellbores from a main wellbore
US20010011593A1 (en) * 1996-11-06 2001-08-09 Wilkins Robert Lee Well completion system with an annular bypass and a solid stopper means
GB2319795B (en) 1996-11-22 2001-01-10 Vetco Gray Inc Abb Insert tree
EP0845577B1 (en) 1996-11-29 2002-07-31 Cooper Cameron Corporation Wellhead assembly
GB2320937B (en) 1996-12-02 2000-09-20 Vetco Gray Inc Abb Horizontal tree block for subsea wellhead
US6050339A (en) 1996-12-06 2000-04-18 Abb Vetco Gray Inc. Annulus porting of horizontal tree
US5868204A (en) 1997-05-08 1999-02-09 Abb Vetco Gray Inc. Tubing hanger vent
US5988282A (en) 1996-12-26 1999-11-23 Abb Vetco Gray Inc. Pressure compensated actuated check valve
US6388577B1 (en) 1997-04-07 2002-05-14 Kenneth J. Carstensen High impact communication and control system
US5927405A (en) 1997-06-13 1999-07-27 Abb Vetco Gray, Inc. Casing annulus remediation system
US6289992B1 (en) 1997-06-13 2001-09-18 Abb Vetco Gray, Inc. Variable pressure pump through nozzle
US6098715A (en) * 1997-07-30 2000-08-08 Abb Vetco Gray Inc. Flowline connection system
WO1999006731A1 (en) 1997-08-04 1999-02-11 Lord Corporation Magnetorheological fluid devices exhibiting settling stability
WO1999018329A1 (en) 1997-10-07 1999-04-15 Fmc Corporation Slimbore subsea completion system and method
US6182761B1 (en) * 1997-11-12 2001-02-06 Exxonmobil Upstream Research Company Flowline extendable pigging valve assembly
WO1999028593A1 (en) 1997-12-03 1999-06-10 Fmc Corporation Rov deployed tree cap for a subsea tree and method of installation
US6138774A (en) 1998-03-02 2000-10-31 Weatherford Holding U.S., Inc. Method and apparatus for drilling a borehole into a subsea abnormal pore pressure environment
EP0952300B1 (en) 1998-03-27 2006-10-25 Cooper Cameron Corporation Method and apparatus for drilling a plurality of offshore underwater wells
US6230824B1 (en) 1998-03-27 2001-05-15 Hydril Company Rotating subsea diverter
US6186239B1 (en) 1998-05-13 2001-02-13 Abb Vetco Gray Inc. Casing annulus remediation system
US7270185B2 (en) 1998-07-15 2007-09-18 Baker Hughes Incorporated Drilling system and method for controlling equivalent circulating density during drilling of wellbores
US6321843B2 (en) * 1998-07-23 2001-11-27 Cooper Cameron Corporation Preloading type connector
US6123312A (en) 1998-11-16 2000-09-26 Dai; Yuzhong Proactive shock absorption and vibration isolation
US6352114B1 (en) * 1998-12-11 2002-03-05 Ocean Drilling Technology, L.L.C. Deep ocean riser positioning system and method of running casing
NO329340B1 (en) 1998-12-18 2010-10-04 Vetco Gray Inc An underwater well device comprising an underwater tree, and a method for coupling an underwater tree to a surface vessel for an overhaul process
US6116784A (en) 1999-01-07 2000-09-12 Brotz; Gregory R. Dampenable bearing
EP1151178A1 (en) 1999-02-11 2001-11-07 Fmc Corporation Subsea completion apparatus
GB2346630B (en) 1999-02-11 2001-08-08 Fmc Corp Flow control package for subsea completions
JP2000251035A (en) 1999-02-26 2000-09-14 Hitachi Ltd Memory card
US6302249B1 (en) 1999-03-08 2001-10-16 Lord Corporation Linear-acting controllable pneumatic actuator and motion control apparatus including a field responsive medium and control method therefor
US6145596A (en) 1999-03-16 2000-11-14 Dallas; L. Murray Method and apparatus for dual string well tree isolation
US7111687B2 (en) 1999-05-14 2006-09-26 Des Enhanced Recovery Limited Recovery of production fluids from an oil or gas well
GB9911146D0 (en) 1999-05-14 1999-07-14 Enhanced Recovery Limited Des Method
GB2347183B (en) * 1999-06-29 2001-02-07 Fmc Corp Flowline connector with subsea equipment package
US6296453B1 (en) 1999-08-23 2001-10-02 James Layman Production booster in a flow line choke
US6450262B1 (en) * 1999-12-09 2002-09-17 Stewart & Stevenson Services, Inc. Riser isolation tool
US6460621B2 (en) * 1999-12-10 2002-10-08 Abb Vetco Gray Inc. Light-intervention subsea tree system
GB2366027B (en) 2000-01-27 2004-08-18 Bell & Howell Postal Systems Address learning system and method for using same
US6457529B2 (en) 2000-02-17 2002-10-01 Abb Vetco Gray Inc. Apparatus and method for returning drilling fluid from a subsea wellbore
WO2001073257A1 (en) 2000-03-24 2001-10-04 Fmc Corporation Tubing head seal assembly
GB2361726B (en) 2000-04-27 2002-05-08 Fmc Corp Coiled tubing line deployment system
GB0020460D0 (en) * 2000-08-18 2000-10-11 Alpha Thames Ltd A system suitable for use on a seabed and a method of installing it
US6557629B2 (en) 2000-09-29 2003-05-06 Fmc Technologies, Inc. Wellhead isolation tool
GB0027269D0 (en) 2000-11-08 2000-12-27 Donald Ian Recovery of production fluids from an oil or gas well
US6494267B2 (en) * 2000-11-29 2002-12-17 Cooper Cameron Corporation Wellhead assembly for accessing an annulus in a well and a method for its use
US6516861B2 (en) * 2000-11-29 2003-02-11 Cooper Cameron Corporation Method and apparatus for injecting a fluid into a well
US6484807B2 (en) * 2000-11-29 2002-11-26 Cooper Cameron Corporation Wellhead assembly for injecting a fluid into a well and method of using the same
US6554075B2 (en) 2000-12-15 2003-04-29 Halliburton Energy Services, Inc. CT drilling rig
US7040408B2 (en) * 2003-03-11 2006-05-09 Worldwide Oilfield Machine, Inc. Flowhead and method
US6457530B1 (en) 2001-03-23 2002-10-01 Stream-Flo Industries, Ltd. Wellhead production pumping tree
GB0110398D0 (en) 2001-04-27 2001-06-20 Alpha Thames Ltd Wellhead product testing system
WO2002097008A2 (en) * 2001-05-25 2002-12-05 Dril-Quip, Inc. Horizontal spool tree assembly
US6612369B1 (en) 2001-06-29 2003-09-02 Kvaerner Oilfield Products Umbilical termination assembly and launching system
US6575247B2 (en) 2001-07-13 2003-06-10 Exxonmobil Upstream Research Company Device and method for injecting fluids into a wellbore
US6763891B2 (en) 2001-07-27 2004-07-20 Abb Vetco Gray Inc. Production tree with multiple safety barriers
US6805200B2 (en) * 2001-08-20 2004-10-19 Dril-Quip, Inc. Horizontal spool tree wellhead system and method
GB0124612D0 (en) 2001-10-12 2001-12-05 Alpha Thames Ltd Single well development system
CA2363974C (en) * 2001-11-26 2004-12-14 Harry Richard Cove Insert assembly for a wellhead choke valve
US6742594B2 (en) * 2002-02-06 2004-06-01 Abb Vetco Gray Inc. Flowline jumper for subsea well
US6719059B2 (en) * 2002-02-06 2004-04-13 Abb Vetco Gray Inc. Plug installation system for deep water subsea wells
US6902005B2 (en) 2002-02-15 2005-06-07 Vetco Gray Inc. Tubing annulus communication for vertical flow subsea well
NO315912B1 (en) 2002-02-28 2003-11-10 Abb Offshore Systems As Underwater separation device for processing crude oil comprising a separator module with a separator tank
US6651745B1 (en) 2002-05-02 2003-11-25 Union Oil Company Of California Subsea riser separator system
US7073592B2 (en) 2002-06-04 2006-07-11 Schlumberger Technology Corporation Jacking frame for coiled tubing operations
US6763890B2 (en) 2002-06-04 2004-07-20 Schlumberger Technology Corporation Modular coiled tubing system for drilling and production platforms
US6840323B2 (en) * 2002-06-05 2005-01-11 Abb Vetco Gray Inc. Tubing annulus valve
CA2404315A1 (en) 2002-09-20 2004-03-20 Dean Edward Moan Well servicing apparatus and method
US7032673B2 (en) 2002-11-12 2006-04-25 Vetco Gray Inc. Orientation system for a subsea well
US6966383B2 (en) 2002-12-12 2005-11-22 Dril-Quip, Inc. Horizontal spool tree with improved porting
NO320179B1 (en) * 2002-12-27 2005-11-07 Vetco Aibel As underwater System
US6907932B2 (en) 2003-01-27 2005-06-21 Drill-Quip, Inc. Control pod latchdown mechanism
US6851478B2 (en) 2003-02-07 2005-02-08 Stream-Flo Industries, Ltd. Y-body Christmas tree for use with coil tubing
CA2423645A1 (en) 2003-03-28 2004-09-28 Larry Bunney Manifold device and method of use for accessing a casing annulus of a well
US7069995B2 (en) 2003-04-16 2006-07-04 Vetco Gray Inc. Remedial system to flush contaminants from tubing string
EP1990505B1 (en) 2003-05-31 2010-09-22 Cameron Systems (Ireland) Limited Apparatus and method for recovering fluids from a well and/or injecting fluids into a well
US6948909B2 (en) 2003-09-16 2005-09-27 Modine Manufacturing Company Formed disk plate heat exchanger
EP1518595B1 (en) * 2003-09-24 2012-02-22 Cameron International Corporation Subsea well production flow and separation system
GB2424913B (en) 2003-10-22 2008-06-18 Vetco Gray Inc Tree Mounted Well Flow Interface Device
ES2344790T3 (en) * 2003-10-23 2010-09-07 Ab Science COMPOUND 2-AMINOARILOXAZOLES AS INHIBITORS OF KINASE THYROSINES.
JP4971797B2 (en) 2003-10-23 2012-07-11 アブ サイエンス 2-Aminoaryloxazole compounds as tyrosine kinase inhibitors
US7000638B2 (en) 2004-01-26 2006-02-21 Honeywell International. Inc. Diverter valve with multiple valve seat rings
DE602005013496D1 (en) * 2004-02-26 2009-05-07 Cameron Systems Ireland Ltd CONNECTION SYSTEM FOR UNDERWATER FLOW SURFACE EQUIPMENT
US7331396B2 (en) 2004-03-16 2008-02-19 Dril-Quip, Inc. Subsea production systems
US7823648B2 (en) 2004-10-07 2010-11-02 Bj Services Company, U.S.A. Downhole safety valve apparatus and method
US7243729B2 (en) 2004-10-19 2007-07-17 Oceaneering International, Inc. Subsea junction plate assembly running tool and method of installation
NO323513B1 (en) 2005-03-11 2007-06-04 Well Technology As Device and method for subsea deployment and / or intervention through a wellhead of a petroleum well by means of an insertion device
US7658228B2 (en) * 2005-03-15 2010-02-09 Ocean Riser System High pressure system
US7770653B2 (en) 2005-06-08 2010-08-10 Bj Services Company U.S.A. Wellbore bypass method and apparatus
CA2617743C (en) * 2005-08-02 2012-03-27 Transocean Offshore Deepwater Drilling, Inc. Modular backup fluid supply system
US7748450B2 (en) 2005-12-19 2010-07-06 Mundell Bret M Gas wellhead extraction system and method
US8079808B2 (en) 2005-12-30 2011-12-20 Ingersoll-Rand Company Geared inlet guide vane for a centrifugal compressor
US7909103B2 (en) 2006-04-20 2011-03-22 Vetcogray Inc. Retrievable tubing hanger installed below tree
US7569097B2 (en) 2006-05-26 2009-08-04 Curtiss-Wright Electro-Mechanical Corporation Subsea multiphase pumping systems
US7699099B2 (en) 2006-08-02 2010-04-20 B.J. Services Company, U.S.A. Modified Christmas tree components and associated methods for using coiled tubing in a well
GB2440940B (en) 2006-08-18 2009-12-16 Cameron Internat Corp Us Wellhead assembly
US7726405B2 (en) 2006-08-28 2010-06-01 Mcmiles Barry James High pressure large bore utility line connector assembly
GB0618001D0 (en) 2006-09-13 2006-10-18 Des Enhanced Recovery Ltd Method
US20080128139A1 (en) 2006-11-09 2008-06-05 Vetco Gray Inc. Utility skid tree support system for subsea wellhead
GB0625191D0 (en) 2006-12-18 2007-01-24 Des Enhanced Recovery Ltd Apparatus and method
GB0625526D0 (en) 2006-12-18 2007-01-31 Des Enhanced Recovery Ltd Apparatus and method
MX2009007472A (en) 2007-01-12 2009-08-17 Bj Services Co Wellhead assembly and method for an injection tubing string.
US8011436B2 (en) 2007-04-05 2011-09-06 Vetco Gray Inc. Through riser installation of tree block
US7596996B2 (en) 2007-04-19 2009-10-06 Fmc Technologies, Inc. Christmas tree with internally positioned flowmeter
US20080302535A1 (en) 2007-06-08 2008-12-11 David Barnes Subsea Intervention Riser System
GB2454807B (en) 2007-11-19 2012-04-18 Vetco Gray Inc Utility skid tree support system for subsea wellhead
ATE545766T1 (en) * 2008-04-21 2012-03-15 Subsea Developing Services As HIGH PRESSURE SLEEVE FOR DOUBLE BORE HIGH PRESSURE RISER PIPE
SG175657A1 (en) * 2008-04-25 2011-11-28 Vetco Gray Inc Subsea toroidal water separator
US8672038B2 (en) 2010-02-10 2014-03-18 Magnum Subsea Systems Pte Ltd. Retrievable subsea bridge tree assembly and method

Also Published As

Publication number Publication date
US20120273214A1 (en) 2012-11-01
US20160160613A1 (en) 2016-06-09
BRPI0508049B1 (en) 2016-05-10
US20170211354A1 (en) 2017-07-27
AU2005216412A1 (en) 2005-09-09
CA2555403A1 (en) 2005-09-09
WO2005083228A1 (en) 2005-09-09
WO2005083228A9 (en) 2005-10-27
NO337264B1 (en) 2016-02-29
US9260944B2 (en) 2016-02-16
NO20063911L (en) 2006-09-01
EP1721058B1 (en) 2009-03-25
DE602005013496D1 (en) 2009-05-07
US8066076B2 (en) 2011-11-29
US10508518B2 (en) 2019-12-17
US20140332222A1 (en) 2014-11-13
BRPI0508049A (en) 2007-07-17
ATE426730T1 (en) 2009-04-15
BRPI0508049B8 (en) 2016-10-11
AU2005216412B2 (en) 2011-03-31
EP1721058A1 (en) 2006-11-15
US8776891B2 (en) 2014-07-15
US20090025936A1 (en) 2009-01-29
US9534474B2 (en) 2017-01-03

Similar Documents

Publication Publication Date Title
US10508518B2 (en) Connection system for subsea flow interface equipment
US6968902B2 (en) Drilling and producing deep water subsea wells
US6742594B2 (en) Flowline jumper for subsea well
US20220003065A1 (en) Apparatus, systems and method for oil and gas operations
US4438817A (en) Subsea well with retrievable piping deck
US8104541B2 (en) Apparatus and method for processing fluids from a well
WO2000047864A1 (en) Subsea completion apparatus
AU2140199A (en) Method and apparatus for drilling a plurality of offshore underwater wells
US20230392466A1 (en) Barrier arrangement in wellhead assembly
US20220290538A1 (en) Subsea pumping and booster system
US9447660B2 (en) Subsea well containment systems and methods
NO20230846A1 (en) Barrier arrangement in wellhead assembly

Legal Events

Date Code Title Description
EEER Examination request