CN101290120B - Gas safe prewarming circulating system - Google Patents

Gas safe prewarming circulating system Download PDF

Info

Publication number
CN101290120B
CN101290120B CN2007100695871A CN200710069587A CN101290120B CN 101290120 B CN101290120 B CN 101290120B CN 2007100695871 A CN2007100695871 A CN 2007100695871A CN 200710069587 A CN200710069587 A CN 200710069587A CN 101290120 B CN101290120 B CN 101290120B
Authority
CN
China
Prior art keywords
pipe
water
preheating
gas
fuel gas
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2007100695871A
Other languages
Chinese (zh)
Other versions
CN101290120A (en
Inventor
周汉强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN2007100695871A priority Critical patent/CN101290120B/en
Publication of CN101290120A publication Critical patent/CN101290120A/en
Application granted granted Critical
Publication of CN101290120B publication Critical patent/CN101290120B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E20/00Combustion technologies with mitigation potential
    • Y02E20/34Indirect CO2mitigation, i.e. by acting on non CO2directly related matters of the process, e.g. pre-heating or heat recovery

Abstract

The invention discloses a fuel gas safe preheating and circulatory system. The system comprises a burner nozzle and a fuel gas pipe; one end of the fuel gas pipe is provided with the burner nozzle; the system also comprises a boiling water conveying pipe, a water preheating pipe, a water return pipe, a water reservoir, a water pump, a preheater and a hot water pipe; the fuel gas pipe and the boiling water conveying pipe are arranged in the water preheating pipe in parallel; one end of the water return pipe is arranged inside the water preheating pipe, while the other end of the water return pipe is connected to the water reservoir; the water reservoir is connected to the preheater by the water pump; and the preheater is connected to the boiling water conveying pipe by the hot water pipe. The fuel gas safe preheating and circulatory system adopts circulating hot water to preheat the fuel gas outside the fuel gas pipe; the flue gas is preheated between 90 and 100 DEG C, then immediately sent to the burner nozzle to be mixed with hot air for reaction; the preheated flue gas can be fully burned and has higher burning efficiency; less flue gas is needed to complete a certain firing operation, thereby saving energy.

Description

A kind of gas safe prewarming circulating system
[technical field]
The present invention relates to gas furnace, relate in particular to gas safe prewarming circulating system in the gas furnace.
[background technology]
For curbing environmental pollution, force without the coal furnace of qualified discharge and to have been stopped using, be that the stove of fuel is widely used with the natural gas of cleaning, oil gas etc.Combustion gas and preheating of air temperature are high more in this class stove, and combustion gas utilizes the diffusion reaction of combustion-supporting combustion air fast more, and mixability is abundant more, and it is complete more to burn, and be more little by the cooling loss that cold combustion gas, cold air produce, thereby make the temperature of combustion product high more.
Present stove all adopts and concentrate preheating in flue, and the mode of disperseing to be transported to each burner then wherein also needs electronic air inducing and air blast.Adopt the preheat temperature of this mode not high, air preheating temperature rests between 300-700 ℃; Hot-air cooling loss unavoidably needs to use more combustion gas keep high temperature in the course of conveying; Air inducing, air blast energy consumption are big.For addressing the above problem, the applicant has also applied for a kind of gas-saving type energy-saving-type gas furnace simultaneously, to the preheating of combustion air overlength, is preheating to maximum temperature and uses immediately, has reduced heat loss.
Simultaneously, all the combustion gas of adopting normal temperature in the present stove, some combustion gas districts are cold-producing medium sky combustion mixing to combustion gas, raising to the combustion product temperature all seriously influences, make fuel gas buring abundant inadequately, efficiency of combustion is low, finishes certain need of work of firing and uses more combustion gas, wastes energy.
[summary of the invention]
Purpose of the present invention solves the problems of the prior art exactly, proposes a kind of gas safe prewarming circulating system, can make the more abundant burning of combustion gas, and the efficiency of combustion height is finished certain need of work of firing and used still less combustion gas, saves the energy.
For achieving the above object, the present invention proposes a kind of gas safe prewarming circulating system, comprise burner, Gas Pipe, one end of described Gas Pipe is provided with burner, also comprise boiling water carrier pipe, preheating water pipe, return pipe, cistern, heat-exchanger pump, preheater and hot-water line, described Gas Pipe and boiling water carrier pipe are set up in parallel in the preheating water pipe, described return pipe one end is arranged on the preheating water pipe, the other end is connected to cistern, described cistern is connected to preheater by heat-exchanger pump, and preheater is connected to the boiling water carrier pipe by hot-water line.
As preferably, also comprise circulating-water valve, described circulating-water valve is arranged between cistern and the heat-exchanger pump.
As preferably, also comprise water valve from the beginning, described water valve from the beginning is arranged on the front end of heat-exchanger pump.
Beneficial effect of the present invention: the present invention adopts circulating hot water that preheating is carried out in combustion gas outside Gas Pipe, between gas-preheating to 90 ℃-100 ℃, and is preheating to the fuel gas inlet place of every burner, immediately with the hot-air hybrid reaction always.The combustion gas of preheating can more abundant burning, and efficiency of combustion is higher, finishes certain need of work of firing and uses still less combustion gas, has saved the energy.The preheat temperature of control combustion gas far below 465 ℃ the burning-point of combustion gas in ignition range, guarantees the safe and reliable of native system between 90 ℃-100 ℃.
Feature of the present invention and advantage will be elaborated in conjunction with the accompanying drawings by embodiment.
[description of drawings]
The structural representation of a kind of gas safe prewarming circulating system of Fig. 1 the present invention.
[specific embodiment]
As shown in Figure 1, a kind of gas safe prewarming circulating system, comprise burner 1, Gas Pipe 2, one end of described Gas Pipe 2 is provided with burner 1, also comprise boiling water carrier pipe 3, preheating water pipe 4, return pipe 5, cistern 6, heat-exchanger pump 9, preheater 10 and hot-water line 11, described Gas Pipe 2 and boiling water carrier pipe 3 are set up in parallel in preheating water pipe 4, described return pipe 5 one ends are arranged in the preheating water pipe 4, the other end is connected to cistern 6, described cistern 6 is connected to preheater 10 by heat-exchanger pump 9, and preheater 10 is connected to boiling water carrier pipe 3 by hot-water line 11.Preheater 10 is arranged in the outer discharge flue of gate mouth, utilizes the fume afterheat in the stove that the water in the preheater 10 is carried out preheating.To be used for the preheating of water through the hot flue gas that stove discharges voluntarily, to hot flue gas function at the present and the past reasonable utilization.
In the combustion gas course of conveying, in boiling water carrier pipe 3, feed hot water, hot water enters preheating water pipe 4 heat is delivered in the Gas Pipe 2, make gas-preheating to 90 ℃ about-100 ℃, through overheated conversion, slightly Jiang Wen water flows in the cistern 6 by return pipe 5, by heat-exchanger pump 9 water is pumped in the preheater 10 then, preheater 10 will be delivered to new hot water in the boiling water carrier pipe 3 by hot-water line 11 behind the water preheat again, so repeatedly circulation.
Also comprise circulating-water valve 7, described circulating-water valve 7 is arranged between cistern 6 and the heat-exchanger pump 9.Circulating-water valve 7 can cut off the output of the water in the cistern 6, stops the circulation of hot water.When the preheat temperature of combustion gas is too high, hot water can be disconnected.Also comprise water valve 8 from the beginning, described water valve from the beginning 8 is arranged on the front end of heat-exchanger pump 9, and when needs were changed intrasystem water, water valve 8 was opened from the beginning, and new running water is input in the system.During work, water valve 8 cuts out from the beginning, and intrasystem water circulates repeatedly.
Combustion gas is in ignition range, and burning-point is at 465 ℃, therefore, is feasible to carrying out preheating without the combustion gas that mixes with air.Present embodiment preferably is controlled at the preheat temperature of combustion gas between 90 ℃-100 ℃, can either guarantee the safe and reliable of system, can make the more abundant burning of combustion gas again, significantly improves the efficiency of combustion of combustion gas.Adopt the present invention can save combustion gas about 20% separately.Adopt this present invention to combine and to save combustion gas about 40% with a kind of gas-saving type energy-saving-type gas furnace of the applicant's application.And needed furnace temperature is high more, and the needed temperature retention time of product is long more, and then energy-saving effect is obvious more, and the solar term rate is high more.About 1450 ℃, fire to use in the kiln of corundum refractory brick and can save combustion gas more than 40%.
The foregoing description is to explanation of the present invention, is not limitation of the invention, any scheme after the simple transformation of the present invention is all belonged to protection scope of the present invention.

Claims (3)

1. gas safe prewarming circulating system, comprise burner (1), Gas Pipe (2), one end of described Gas Pipe (2) is provided with burner (1), it is characterized in that: also comprise boiling water carrier pipe (3), preheating water pipe (4), return pipe (5), cistern (6), heat-exchanger pump (9), preheater (10) and hot-water line (11), described Gas Pipe (2) and boiling water carrier pipe (3) are set up in parallel in preheating water pipe (4), described return pipe (5) one ends are arranged on the preheating water pipe (4), the other end is connected to cistern (6), described cistern (6) is connected to preheater (10) by heat-exchanger pump (9), and preheater (10) is connected to boiling water carrier pipe (3) by hot-water line (11).
2. a kind of gas safe prewarming circulating system as claimed in claim 1 is characterized in that: also comprise circulating-water valve (7), described circulating-water valve (7) is arranged between cistern (6) and the heat-exchanger pump (9).
3. a kind of gas safe prewarming circulating system as claimed in claim 1 is characterized in that: also comprise water valve (8) from the beginning, described water valve from the beginning (8) is arranged on the front end of heat-exchanger pump (9).
CN2007100695871A 2007-08-03 2007-08-03 Gas safe prewarming circulating system Expired - Fee Related CN101290120B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2007100695871A CN101290120B (en) 2007-08-03 2007-08-03 Gas safe prewarming circulating system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2007100695871A CN101290120B (en) 2007-08-03 2007-08-03 Gas safe prewarming circulating system

Publications (2)

Publication Number Publication Date
CN101290120A CN101290120A (en) 2008-10-22
CN101290120B true CN101290120B (en) 2010-06-09

Family

ID=40034487

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2007100695871A Expired - Fee Related CN101290120B (en) 2007-08-03 2007-08-03 Gas safe prewarming circulating system

Country Status (1)

Country Link
CN (1) CN101290120B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3717139A (en) * 1969-11-28 1973-02-20 Gaz De France Submerged combustion heat-generator
US5678408A (en) * 1993-10-19 1997-10-21 California Energy Commission Performance enhanced gas turbine powerplants
CN1737351A (en) * 2005-09-01 2006-02-22 西安交通大学 System and method for improving efficiency of combined cycle electric power plant
EP1065347B1 (en) * 1999-07-01 2007-03-07 General Electric Company Method for fuel gas moisturization and heating
CN201069163Y (en) * 2007-08-03 2008-06-04 周汉强 Gas safe preheating and circulation system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3717139A (en) * 1969-11-28 1973-02-20 Gaz De France Submerged combustion heat-generator
US5678408A (en) * 1993-10-19 1997-10-21 California Energy Commission Performance enhanced gas turbine powerplants
EP1065347B1 (en) * 1999-07-01 2007-03-07 General Electric Company Method for fuel gas moisturization and heating
CN1737351A (en) * 2005-09-01 2006-02-22 西安交通大学 System and method for improving efficiency of combined cycle electric power plant
CN201069163Y (en) * 2007-08-03 2008-06-04 周汉强 Gas safe preheating and circulation system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
JP特開2000-121146A 2000.04.28

Also Published As

Publication number Publication date
CN101290120A (en) 2008-10-22

Similar Documents

Publication Publication Date Title
CN103343965B (en) A kind of reheat furnace system utilizing oxygen-enriched combusting
CN207222272U (en) Coating workshop RTO two level residual neat recovering systems
CN103438478B (en) Aluminium melting furnace rotary heat accumulating type burner
CN106895390A (en) A kind of station boiler multi-element heterogeneous afterheat utilizing system
CN206682921U (en) A kind of station boiler multi-element heterogeneous afterheat utilizing system
CN201069163Y (en) Gas safe preheating and circulation system
CN101928797A (en) High-blast-temperature energy-saving and emission-reducing combined type preheating system for blast furnace
CN101290120B (en) Gas safe prewarming circulating system
CN102381830B (en) A kind of method and system of supporting combustion by using oxygen-enriched air in production of float glass
CN100458290C (en) Apparatus for refrigeration or pyrogenicity or sanitary hot water using generator exhaust or residual heat
CN203454110U (en) Heating furnace system utilizing oxygen-enriched combustion
CN203174129U (en) Flue gas self-circulation combustion system of blast furnace hot blast stove
CN201785422U (en) High-air-temperature energy-saving emission-reduction combined preheating system of blast furnace
CN102078855A (en) Drying residual-heat utilization device of large-scale automobile coating production line
CN202012962U (en) High-efficiency automatic energy-saving hot water stove
CN204901904U (en) Gas boiler or full heat recovery system of direct combustion machine flue gas waste heat
CN210241595U (en) Organic waste gas treatment device
CN208671326U (en) Combustion heat-exchange device, burnt gas wall hanging furnace and gas heater
CN208349268U (en) A kind of combination energy steam generator
CN105066219A (en) Total flue gas waste heat recovery system and method for gas boiler or direct-fired machine
CN204593429U (en) Split combustion type gas steam boiler gas saving system
CN208920856U (en) Energy-saving fuel gas
CN103776077B (en) A kind of domestic distributed energy blood circulation
CN204460406U (en) A kind of recovery oil-burning gas-fired boiler tail gas heat quantity device
CN212618309U (en) Burner for preheating combustion-supporting air by using combustion tail gas

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Assignee: Changxing Furnace Material Co., Ltd.

Assignor: Zhou Hanqiang

Contract record no.: 2011330000016

Denomination of invention: Gas safe prewarming circulating system

Granted publication date: 20100609

License type: Exclusive License

Open date: 20081022

Record date: 20110107

C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100609

Termination date: 20130803