WO2001049949A2 - Shear wall construction - Google Patents

Shear wall construction Download PDF

Info

Publication number
WO2001049949A2
WO2001049949A2 PCT/US2000/034107 US0034107W WO0149949A2 WO 2001049949 A2 WO2001049949 A2 WO 2001049949A2 US 0034107 W US0034107 W US 0034107W WO 0149949 A2 WO0149949 A2 WO 0149949A2
Authority
WO
WIPO (PCT)
Prior art keywords
sheet
channel
track
shear wall
studs
Prior art date
Application number
PCT/US2000/034107
Other languages
French (fr)
Other versions
WO2001049949A3 (en
Inventor
Ronald Donald Lucey
Ronald Nelson
David A. Brown
Original Assignee
Zone Four, Llc
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zone Four, Llc filed Critical Zone Four, Llc
Priority to AU21061/01A priority Critical patent/AU2106101A/en
Publication of WO2001049949A2 publication Critical patent/WO2001049949A2/en
Publication of WO2001049949A3 publication Critical patent/WO2001049949A3/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/26Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24CDOMESTIC STOVES OR RANGES ; DETAILS OF DOMESTIC STOVES OR RANGES, OF GENERAL APPLICATION
    • F24C3/00Stoves or ranges for gaseous fuels
    • F24C3/002Stoves
    • F24C3/006Stoves simulating flames
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/24Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of metal
    • E04B2001/2496Shear bracing therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/26Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
    • E04B1/2604Connections specially adapted therefor
    • E04B2001/268Connection to foundations
    • E04B2001/2684Connection to foundations with metal connectors
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/26Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of wood
    • E04B2001/2696Shear bracing
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y10TECHNICAL SUBJECTS COVERED BY FORMER USPC
    • Y10STECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y10S52/00Static structures, e.g. buildings
    • Y10S52/11Mobile-structure stabilizing anchor

Definitions

  • the present invention relates generally to shear wall constructions, and more particularly to methods and structures for vertically tying fabricated shear wall segments through floor and ceiling structures.
  • fabricated wall segments are sometimes built separately and erected on site and are sometimes built on site while coordinated with other aspects of building construction.
  • Fabricated shear walls need to be connected not only to each other but also to underlying and overlying structural elements, such as floors and roofs.
  • a building 10 comprising a plurality of wall sections 1 1 is schematically illustrated in cross section During an earthquake, like any other building structural elements, these wall segments are subject to various stresses
  • Wall segments 12 near building corners, in particular, are subjected to vertical stresses as the central portions of the wall act as a fulcrum Because these vertical stresses are directed towards horizontal nailing that hold the structures together, corner wall segments 12 are typically referred to as shear walls 12.
  • hold-down devices are often provided to connect the vertical portions of a shear wall 12 to other adjacent building structural elements. While conventional hold-down devices, framing configurations and other connection hardware somewhat assist the ability of shear walls to resist seismic stresses, a need exists for further improvement.
  • the present invention provides a shear wall construction that includes close laterally-spaced pairs of vertical studs or posts on each lateral side of a shear wall sheet (e.g., plywood).
  • a channel defining member is fitted between and affixed to the spaced studs.
  • a tie member extends from the channel defining member into a vertically adjacent building structural element
  • the channel defining member generally comprises metal or other structural material, and defines a longitudinal channel generally parallel to the studs
  • the member is a generally tubular element, though in other arrangements the member can comprise a generally C- or U-shaped element.
  • the preferred tie member is a threaded rod that extends from an end plate of the channel-defining member and into a concrete foundation or floor. Similar constructions are provided at opposite lateral ends of the shear wall, such that the shear wall can better resist seismic forces
  • the preferred embodiments provide a bottom track for aiding and reinforcing the vertical connection.
  • the bottom track comprises two longitudinal flanges with a plurality of fastener holes therein, and a central longitudinal portion having punched-through holes. The punched-through holes provide downwardly extending protrusions
  • the bottom track is positioned over a concrete form with the flared protrusions from the punched-through holes extending downwardly into a region in which a concrete floor will be formed.
  • the tie members extend through the track into the concrete form. Concrete is then allowed to harden around the tie member and track protrusions, such that the bottom track is secured to the concrete floor.
  • the shear wall is then erected over the track and flanges are folded up and fixed to sheat the bottom edge of the shear wall.
  • Figure 1 is a schematic horizontal cross section of a portion of a building having segmented walls;
  • Figure 2A is a rear elevational view of a pre-fabricated shear wall constructed in accordance with a first embodiment of the present invention;
  • Figure 2B is a rear elevational view of a shear wall constructed in accordance with a second embodiment of the present invention;
  • Figure 2C is a rear elevational view of two spliced shear wall panels, constructed in accordance with a third embodiment of the present invention.
  • Figure 3 is a side elevational cross-section taken along lines 3-3 of Figure 2A;
  • Figure 4 is an enlarged view of a lower corner of a shear wall constructed in accordance with the preferred embodiments, showing a channel-defining member sandwiched between two closely spaced studs and having a threaded member extending from the channel-defining member through a concrete floor;
  • Figure 5 is a partial plan view of a bottom track for sheathing the lower sill of a shear wall, constructed in accordance with a preferred embodiment of the present invention, prior to assembly;
  • Figure 6 is a flow chart generally illustrating a method of assembling the preferred shear wall construction.
  • Figure 7 is an enlarged sectional view of two shear walls connected through a floor.
  • the shear wall 12a includes a sheet of wall material, which in the illustrated embodiment comprises plywood having dimensions of about 4 feet (width) by 8 feet (height).
  • the shear wall 12a is shown erected over and tied down to a vertically-adjacent structural element, in the illustrated embodiment comprising a concrete foundation 21a.
  • the vertically-adjacent structural element can comprise a floor between stories of a building, and the shear wall can also be tied through a floor to a second shear wall in a lower story.
  • the wall sheet 20a is reinforced by end studs or posts 22a running longitudinally along the height of the rear or back side of the shear wall 12a.
  • One such end stud 22a is shown at each lateral end of the shear wall 12a, nailed into the plywood sheet 20a along its length at preferred nail spacings between about 2 inches and 6 inches (about 4 inches shown).
  • each of the studs 22a comprise "2 by 4" timbers (actual dimensions about 1.5 inches by 3.5 inches).
  • the shear wall 12a also includes an offset stud or post 24a extending parallel and spaced laterally inward from each of the end studs 22a, on the same side of the wall sheet 20a.
  • the offset stud 24a also comprises a 2-by-4 timber in the illustrated embodiment, nailed along its length to the plywood sheet 20a.
  • the offset studs 24a are close to the end studs 22a so as to effectively transfer loads at the shear wall corners, but sufficiently spaced from their corresponding end studs 22a so as to independently transfer loads to the plywood sheet 20a.
  • the studs 22a and 24a are spaced by between about 1 inch and 6 inches, more preferably between about 2 inches and 3 inches.
  • the studs 22a and 24a are spaced by about 3 inches.
  • Reinforcing blocks 25a (1.5" x 3.5" x 3") are also shown between the studs 22a and 24a, located about a quarter of the height up the shear wall 12a.
  • intermediate studs or posts 26a between the spaced pairs of studs 22a, 24a proximate the lateral ends of the shear wall 12a. Nailing can be less dense for the intermediate studs 26a, and is shown with 12 inchss between nails. In the illustrated embodiment, these intermediate studs 26a are spaced from each other and from the lateral ends studs 22a by about one third of shear wall width, or 16 inches for the 4" by 8' wall shown.
  • top plate Extending over the tops of the studs 22a, 24a, 26a is a top plate.
  • the top plate comprises two stacked plates, 28a and 30a, which also aids in stiffening the shear wall 12a.
  • the plates 28a and 30a each comprise 2-by-4 timbers (actual dimensions about 1.5 inches by 3.5 inches).
  • a similar bottom plate or sill 32a extends below the bottoms of the studs 22a, 24a, 26a.
  • the 32a preferably sits within a bottom track 34a, which wraps around the bottom, front and back of the plate 32a, as best seen from the sectional view of Figure 3.
  • the track 34a is preferably nailed along the back of the bottom plate 32a and the front of the plywood sheet 20a.
  • the track 34a is fixed to the underlying concrete foundation 21a, as described in more detail with respect to Figures 3-5.
  • a channel-defining member 40 and a tie member 42 tie the shear wall 12a to the vertically-adjacent building structural element 21 a, at each lateral end of the shear wall 12a.
  • the channel-defining member 40 is fixed between the closely spaced end stud 22a and offset stud 24a, while the tie member 42 is fixed to and extends between the channel-defining member 40 and the vertically adjacent building structural element 21a.
  • the channel of the channel-defining member 40 and tie member 42 each extend generally parallel with the studs 22a and 24a between which the member 40 is sandwiched.
  • the channel-defining member 40 and tie member 42 will be described in more detail below with respect to Figure 4 below.
  • a shear wall 12b is illustrated in accordance with a second preferred embodiment.
  • the second embodiment is similar to the first embodiment. Accordingly, like parts are referenced by like reference numerals, with the exception that reference numerals of corresponding parts include the suffix "b" in place of the suffix a
  • shear wall 12b of the second embodiment has dimensions of about 2 feet by 8 feet, rather than 4 feet by 8 feet. Due to its narrower dimensions, the shear wall 12b does not include intermediate studs.
  • the construction can be otherwise identical to that of the first embodiment, with commensurate dimensional changes in corresponding elements in the horizontal dimension
  • a shear wall 12c is illustrated in accordance with a third preferred embodiment
  • the third embodiment is similar to the first and second embodiments. Accordingly, like parts are referenced by like reference numerals, with the exception that reference numerals of corresponding parts include the suffix "c" in place of the suffixes "a" or "b"
  • the shear wall 12c of the third embodiment comprises two sheets 20c, each comprising a sheet of plywood [e.g., 4 feet by 8 feet), joined at a plywood splice 44c
  • the wall 12c thus has overall dimensions of 8 feet by 8 feet.
  • the splice 44c can have a conventional construction, but in the preferred embodiment includes a strap, e.g., about 4 inches wide, overlapping both sheets 20c along the front side. The strap is alternately fastened, in staggered fashion along the height of the wall 12c, to each of the sheets 20c, preferably by nailing.
  • Each sheet 20c includes two intermediate studs 26c, similar to those of the first embodiment.
  • the construction can be otherwise identical to that of the first embodiment, with commensurate dimensional changes in corresponding elements in the horizontal dimension.
  • an enlarged view is provided of a corner of the shear wall 12a and the vertically-adjacent building structural member 21 a
  • the channel defining member 40 defines a longitudinal channel and a mounting platform extending across the channel, both preferably comprising a heavy structural material.
  • the member 40 comprises a generally tubular member commercially available from Zone Four, LLC of San Leandro, CA under the trade name Tension TieTM or T2TM.
  • Zone Four, LLC of San Leandro, CA under the trade name Tension TieTM or T2TM.
  • a similar structure is referred to as a "Continuity Tie" in U.S Patent No.
  • the illustrated member 40 includes only one end plate 50, and the tie member 42 is centered relative to the channel defining member 40, rather than offset.
  • the illustrated channel-defining member 40 comprises 1 /8 inch tube steel, formed into a 3" by 3" square cross-section tube of about six inches in length
  • the illustrated end plate 50 comprises a 3" by 3.5" plate of 3/8- ⁇ nch steel welded to the tube steel.
  • the channel defining member 40 can have other constructions without departing from the spirit of the present invention.
  • the channel defining member can be a C shaped or U-shaped member, and in such arrangements the channel can open inwardly (toward the sheet 20a), outwardly or to one side (toward one of the studs 22a, 24a).
  • the hollow configuration facilitates connection as will be understood from the disclosure herein.
  • the channel defining member can be replaced by a solid block or plate of material capable of being connected between studs and to vertically adjacent structures as described herein, in which case no separate mounting platform would be employed
  • the mounting platform can comprise an end plate on the lower end of the channel defining member, two end plates, or an intermediate plate bar orplura ty of bars extending across the channel between the ends of the channel defining member
  • the tie member 42 preferably comprises a tension resistant member, particularly a threaded rod in the illustrated embodiment
  • the tie member 42 comprises a structural material, such as forged steel, having a diameter preferably between about 0 25 inch and 2 inches, and is about 0.75 inch in the illustrated embodiment.
  • the tension resistant member can comprise a cable
  • the illustrated tie member 42 is fixed to the end plate 50, preferably by extending through a mounting aperture centered in the end plate 50 and applying a nut 52 on the distal or upper side of the end plate 50
  • the illustrated tie member 42 extends from the end plate 50, connected in tension resistant manner on the upper side of the end plate 50, through the channel of the channel defining member 40, through the bottom plate 32a and bottom track 34a, and into the concrete foundation 21 a If the mounting platform is located at the lower end or at an intermediate location in the channel-defining member, the nut is still located on the distal side of the channel defining member, but within the channel.
  • the hollow, tubular nature of the channel defining member particularly facilitates access for the connection.
  • the illustrated tie member 42 includes two coaxial members joined by a coupler 59, as will be better understood from the discussion of assembly below
  • connection can be tension and compression resistant.
  • modification of the illustrated embodiment, where the tie member 42 comprises a stiff rod can involve simple addition of a second nut on the proximal or bottom side of the end plate 50 More preferably, tension and compression resistance can be further enhanced by addition of a second mounting platform, such as a second end plate with nuts on the bottom or both sides fixing the tie member to the second end plate
  • the tie member 42 can attach at the mounting platform by any suitable manner (e g welding, looping nut and washer, etc )
  • the channel defining member 40 is fixed to each of the end stud 22a and offset stud 24a between which it is sandwiched
  • bolts holes in the channel defining member 40 sidewalls are preferably staggered on either side of the tie member 42 that extends through the channel.
  • a plurality of bolts 54 extend through each of the end stud 22a the bolt mounting apertures of the channel defining member 40 and the offset stud 24a
  • the bolts 54 are then affixed by nuts 56, preferably on the side of the offset studs 24a, while bolt heads 58 preferably abut the end studs 22a
  • the channel defining member can be fixed to the studs 22a, 24a by means of other fasteners, such as nails, screws, rivets, etc.
  • the bottom track 34a is illustrated in more detail.
  • the longitudinal dimension of the track 34a extends across the lateral dimension of the shear wall 12a when assembled.
  • the track 34a is shown prior to assembly, comprising a strip of sheet metal, preferably between about 10 gauge and 30 gauge steel (16 gauge in the illustrated embodiment).
  • the unassembled track 34a of Figure 5 illustrates three lateral zones, preferably separated by fold creases.
  • a first or central zone 60 comprises a plurality of longitudinally separated through holes 62. Desirably, the central zone 60 is wide enough to underlie the bottom plate 42 and sheet 20a (see Figure 3). As best seen from the sectional view of an assembled shear wall in Figure 4, the through holes 62 are formed by punching holes through the sheet metal, such that protrusions or flares 63 left by the punching process extend below the track 34a.
  • the punched- through holes 62 preferably have a width or diameter between about 0.25 inch and 3 inches, more preferably between about 1 inch and 1.5 inches
  • the holes 62 are preferably spaced by between about 1 inch and 12 inches, about 4 inches in the illustrated embodiment
  • Through holes 62 at longitudinal ends of the track 34a, corresponding to lateral ends of the shear wall 12a, are preferably located to serve as templates for placement of the tie member 42, as will be better understood from the discussion of assembly below.
  • the unassembled track 34a also comprises sidewall zones 64 on either lateral side of the central zone 60.
  • Each sidewall zone 64 preferably comprises a plurality of fastener holes 66.
  • fastener holes 66 preferably have diameters between about 0.1 inch and 0.25 inch to facilitate nailing therethrough.
  • the fastener holes 66 are staggered between upper and lower portions of the sidewalls 64 to distribute stress.
  • partial building construction leaves a frame or opening for the shear wall 12a and a concrete form for the floor 21a.
  • the track 34a is then positioned 100 and preferably temporarily fixed over the concrete form, either before pouring the concrete or after pouring and before hardening ("wet set").
  • the protrusions or flares 63 extend downwardly from the through holes 62 into wet concrete.
  • the tie members 42 are preferably extended 1 10 through selected through holes 62 at longitudinal ends of the track 34a, into the concrete form (also either prior to pouring or wet set within the concrete), protruding upwardly a few inches above the track 34a.
  • the concrete is allowed to harden 120 around the protrusions 63 and the tie member 42.
  • the shear wall 12a is then erected 130 over the track 34a.
  • the skilled artisan will appreciate that the wall 12a can be assembled during construction (on site assembly) or prior to erection 130 and tying to other elements of the building (pre manufactured assembly).
  • pre-manufactured assembly involves affixing the end and offset studs 22a, 24a, any intermediate studs 26a, top plates 28a, 30a and bottom plate 32a to the sheet
  • the channel defining member 40 is bolted between the spaced pair of studs 22a, 24a. Once assembled the pre manufactured shear wall 12a can then be lifted or erected 130 into place over the track 34a. The tie members 42 protrude upwardly through holes in the bottom plate 32a. These tie members 42 can then be affixed 140 to the channel defining member 40, such as by coupling an extension to the portion of the members protruding through the track 34a and bottom plate 32a, and then threading the nut 52 over the member 42 until engaging the end plate 50
  • An exemplary on site assembly involves first assembly the outside or end studs 22a, top plate 28a, 30a and bottom plate 32a This structure can be lifted into place within the frame or opening for the shear wall 12a, with the tie member 42 protruding upwardly through holes in the bottom plate 32a, and the shear wall 12a is braced in position
  • the channel defining members 40 can be temporarily nailed in place inside the end studs 22a while bolt holes are drilled through the studs 22a
  • the offset studs 24a are then inserted into the framework adjacent the channel defining members 40, the studs 24a are toe nailed into the plates 28a, 32a, and bolt holes are drilled through the offset studs 24a
  • the tie member 42 can then be affixed 140 to the channel defining member 40, such as by coupling an extension to the portion of the member 42 protruding through the member.
  • the wall sheet 20a can be last affixed and nailed to the various studs and plates while erected over the track 34a.
  • the track 34a preferably sheaths 150 the bottom edge of the shear wall 12a.
  • the track 34a is folded along longitudinal crease lines separating the central zone 60 from the sidewall zones 64.
  • the sidewall zones 64 are folded up 90° to the central zone 60, thereby forming a generally U-shaped track (see Figure 3)
  • the sidewall zones 64 are affixed to the sheet 20a and bottom plate 32a, preferably by nailing through the fastener holes 66
  • a the tie member 42 can be affixed to a mounting platform 50d of a first channel defining member 40d, such as by a nut 52d on a distal (upper) side of the platform 50d.
  • the channel defining member 40d is sandwiched between an end post or stud 22d and an offset stud 24d of a shear wall 12d
  • the tie member 42 can be extended through a floor 21 d and affixed to a second channel-defining member 403 sandwiched between studs 22e, 24e of a shear wall 12e in the story below.
  • the tie member 42 would then be affixed to a mounting platform 50e of the second channel-defining member 40e, such as by a nut 52e on a distal (lower) side of the platform 50e It will be understood that the tie member can be a single, continuous member, or it can comprises a plurality of coupled members (not shown).

Abstract

A shear wall construction and method for assembling the same is disclosed. A plywood sheet (20a) includes close laterally-spaced pairs of vertical studs or posts (22a, 24a) proximate each lateral end. A channel-defining member (40) is fitted and fixed between the spaced studs (22a, 24a). A tie member (42) extends from the channel-defining member (40) into a concrete foundation (21a) or other underlying building element. A track (34a) is also provided for sheathing a lower edge of the shear wall (12a). Protrusions from the metal track (34a) aid in anchoring the shear wall (12a) to the concrete foundation (21a).

Description

SHEAR WALL CONSTRUCTION
Field of the Invention The present invention relates generally to shear wall constructions, and more particularly to methods and structures for vertically tying fabricated shear wall segments through floor and ceiling structures. Background of the Invention
In the construction of buildings, fabricated wall segments are sometimes built separately and erected on site and are sometimes built on site while coordinated with other aspects of building construction. Fabricated shear walls need to be connected not only to each other but also to underlying and overlying structural elements, such as floors and roofs. With reference to Figure 1 , a building 10 comprising a plurality of wall sections 1 1 is schematically illustrated in cross section During an earthquake, like any other building structural elements, these wall segments are subject to various stresses Wall segments 12 near building corners, in particular, are subjected to vertical stresses as the central portions of the wall act as a fulcrum Because these vertical stresses are directed towards horizontal nailing that hold the structures together, corner wall segments 12 are typically referred to as shear walls 12. In order to resist stresses to which shear walls 12 are subjected, hold-down devices are often provided to connect the vertical portions of a shear wall 12 to other adjacent building structural elements. While conventional hold-down devices, framing configurations and other connection hardware somewhat assist the ability of shear walls to resist seismic stresses, a need exists for further improvement.
Summary of the Invention In satisfaction of this need, the present invention provides a shear wall construction that includes close laterally-spaced pairs of vertical studs or posts on each lateral side of a shear wall sheet (e.g., plywood). A channel defining member is fitted between and affixed to the spaced studs. A tie member extends from the channel defining member into a vertically adjacent building structural element
The channel defining member generally comprises metal or other structural material, and defines a longitudinal channel generally parallel to the studs In the illustrated embodiments, the member is a generally tubular element, though in other arrangements the member can comprise a generally C- or U-shaped element. The preferred tie member is a threaded rod that extends from an end plate of the channel-defining member and into a concrete foundation or floor. Similar constructions are provided at opposite lateral ends of the shear wall, such that the shear wall can better resist seismic forces Additionally, the preferred embodiments provide a bottom track for aiding and reinforcing the vertical connection. In particular, the bottom track comprises two longitudinal flanges with a plurality of fastener holes therein, and a central longitudinal portion having punched-through holes. The punched-through holes provide downwardly extending protrusions
In operation, the bottom track is positioned over a concrete form with the flared protrusions from the punched-through holes extending downwardly into a region in which a concrete floor will be formed. Similarly, the tie members extend through the track into the concrete form. Concrete is then allowed to harden around the tie member and track protrusions, such that the bottom track is secured to the concrete floor. The shear wall is then erected over the track and flanges are folded up and fixed to sheat the bottom edge of the shear wall.
Brief Description of the Drawings These and other aspects of the invention will be readily apparent from the detailed description below and from the attached drawings, meant to illustrate and not to limit the invention, and wherein:
Figure 1 is a schematic horizontal cross section of a portion of a building having segmented walls; Figure 2A is a rear elevational view of a pre-fabricated shear wall constructed in accordance with a first embodiment of the present invention; Figure 2B is a rear elevational view of a shear wall constructed in accordance with a second embodiment of the present invention;
Figure 2C is a rear elevational view of two spliced shear wall panels, constructed in accordance with a third embodiment of the present invention;
Figure 3 is a side elevational cross-section taken along lines 3-3 of Figure 2A; Figure 4 is an enlarged view of a lower corner of a shear wall constructed in accordance with the preferred embodiments, showing a channel-defining member sandwiched between two closely spaced studs and having a threaded member extending from the channel-defining member through a concrete floor;
Figure 5 is a partial plan view of a bottom track for sheathing the lower sill of a shear wall, constructed in accordance with a preferred embodiment of the present invention, prior to assembly; Figure 6 is a flow chart generally illustrating a method of assembling the preferred shear wall construction; and
Figure 7 is an enlarged sectional view of two shear walls connected through a floor.
Detailed Description of the Preferred Embodiment Although described with reference to preferred embodiments in the context of shear walls over concrete foundations, the skilled artisan will readily find application for the methods and structures disclosed in other contexts. For example, and without limitation, the methods and structures can be readily applied to tying shear walls through floors between stories in a building, as described in more detail with respect to Figure 7.
With reference now to Figures 2A and 3, a shear wall 12a is illustrated in accordance with a first preferred embodiment. The shear wall 12a includes a sheet of wall material, which in the illustrated embodiment comprises plywood having dimensions of about 4 feet (width) by 8 feet (height). The shear wall 12a is shown erected over and tied down to a vertically-adjacent structural element, in the illustrated embodiment comprising a concrete foundation 21a. In other arrangements, as noted, the vertically-adjacent structural element can comprise a floor between stories of a building, and the shear wall can also be tied through a floor to a second shear wall in a lower story.
The wall sheet 20a is reinforced by end studs or posts 22a running longitudinally along the height of the rear or back side of the shear wall 12a. One such end stud 22a is shown at each lateral end of the shear wall 12a, nailed into the plywood sheet 20a along its length at preferred nail spacings between about 2 inches and 6 inches (about 4 inches shown). In the illustrated embodiment, each of the studs 22a comprise "2 by 4" timbers (actual dimensions about 1.5 inches by 3.5 inches).
The shear wall 12a also includes an offset stud or post 24a extending parallel and spaced laterally inward from each of the end studs 22a, on the same side of the wall sheet 20a. The offset stud 24a also comprises a 2-by-4 timber in the illustrated embodiment, nailed along its length to the plywood sheet 20a. Desirably, the offset studs 24a are close to the end studs 22a so as to effectively transfer loads at the shear wall corners, but sufficiently spaced from their corresponding end studs 22a so as to independently transfer loads to the plywood sheet 20a. Preferably, the studs 22a and 24a are spaced by between about 1 inch and 6 inches, more preferably between about 2 inches and 3 inches. In the illustrated embodiment, the studs 22a and 24a are spaced by about 3 inches. Reinforcing blocks 25a (1.5" x 3.5" x 3") are also shown between the studs 22a and 24a, located about a quarter of the height up the shear wall 12a.
Preferably, further stiffening is provided by intermediate studs or posts 26a between the spaced pairs of studs 22a, 24a proximate the lateral ends of the shear wall 12a. Nailing can be less dense for the intermediate studs 26a, and is shown with 12 inchss between nails. In the illustrated embodiment, these intermediate studs 26a are spaced from each other and from the lateral ends studs 22a by about one third of shear wall width, or 16 inches for the 4" by 8' wall shown.
Extending over the tops of the studs 22a, 24a, 26a is a top plate. In the illustrated embodiment, the top plate comprises two stacked plates, 28a and 30a, which also aids in stiffening the shear wall 12a. In the illustrated embodiment, the plates 28a and 30a each comprise 2-by-4 timbers (actual dimensions about 1.5 inches by 3.5 inches).
A similar bottom plate or sill 32a extends below the bottoms of the studs 22a, 24a, 26a. The bottom plate
32a preferably sits within a bottom track 34a, which wraps around the bottom, front and back of the plate 32a, as best seen from the sectional view of Figure 3. As illustrated, the track 34a is preferably nailed along the back of the bottom plate 32a and the front of the plywood sheet 20a. The track 34a is fixed to the underlying concrete foundation 21a, as described in more detail with respect to Figures 3-5.
Referring again to Figure 2A, a channel-defining member 40 and a tie member 42 tie the shear wall 12a to the vertically-adjacent building structural element 21 a, at each lateral end of the shear wall 12a. The channel-defining member 40 is fixed between the closely spaced end stud 22a and offset stud 24a, while the tie member 42 is fixed to and extends between the channel-defining member 40 and the vertically adjacent building structural element 21a. The channel of the channel-defining member 40 and tie member 42 each extend generally parallel with the studs 22a and 24a between which the member 40 is sandwiched. The channel-defining member 40 and tie member 42 will be described in more detail below with respect to Figure 4 below.
With reference now to Figure 2B, a shear wall 12b is illustrated in accordance with a second preferred embodiment. The second embodiment is similar to the first embodiment. Accordingly, like parts are referenced by like reference numerals, with the exception that reference numerals of corresponding parts include the suffix "b" in place of the suffix a
The basic difference between the shear wall 12a of the first embodiment and the shear wall 12b of the second embodiment is that the illustrated shear wall 12b has dimensions of about 2 feet by 8 feet, rather than 4 feet by 8 feet. Due to its narrower dimensions, the shear wall 12b does not include intermediate studs. The construction can be otherwise identical to that of the first embodiment, with commensurate dimensional changes in corresponding elements in the horizontal dimension
With reference now to Figure 2C, a shear wall 12c is illustrated in accordance with a third preferred embodiment The third embodiment is similar to the first and second embodiments. Accordingly, like parts are referenced by like reference numerals, with the exception that reference numerals of corresponding parts include the suffix "c" in place of the suffixes "a" or "b"
The shear wall 12c of the third embodiment comprises two sheets 20c, each comprising a sheet of plywood [e.g., 4 feet by 8 feet), joined at a plywood splice 44c The wall 12c thus has overall dimensions of 8 feet by 8 feet. The splice 44c can have a conventional construction, but in the preferred embodiment includes a strap, e.g., about 4 inches wide, overlapping both sheets 20c along the front side. The strap is alternately fastened, in staggered fashion along the height of the wall 12c, to each of the sheets 20c, preferably by nailing. Each sheet 20c includes two intermediate studs 26c, similar to those of the first embodiment. The construction can be otherwise identical to that of the first embodiment, with commensurate dimensional changes in corresponding elements in the horizontal dimension. With reference now to Figure 4, an enlarged view is provided of a corner of the shear wall 12a and the vertically-adjacent building structural member 21 a The channel defining member 40 defines a longitudinal channel and a mounting platform extending across the channel, both preferably comprising a heavy structural material. In the illustrated embodiment, the member 40 comprises a generally tubular member commercially available from Zone Four, LLC of San Leandro, CA under the trade name Tension Tie™ or T2™. A similar structure is referred to as a "Continuity Tie" in U.S Patent No. 5,921,042 ("the '042 patent"), the disclosure of which is expressly incorporated herein by reference. Unlike the Continuity Tie™ of the '042 patent, the illustrated member 40 includes only one end plate 50, and the tie member 42 is centered relative to the channel defining member 40, rather than offset. The illustrated channel-defining member 40 comprises 1 /8 inch tube steel, formed into a 3" by 3" square cross-section tube of about six inches in length The illustrated end plate 50 comprises a 3" by 3.5" plate of 3/8-ιnch steel welded to the tube steel.
The skilled artisan will readily appreciate that the channel defining member 40 can have other constructions without departing from the spirit of the present invention. For example, in alternative arrangements, the channel defining member can be a C shaped or U-shaped member, and in such arrangements the channel can open inwardly (toward the sheet 20a), outwardly or to one side (toward one of the studs 22a, 24a). Advantageously, the hollow configuration facilitates connection as will be understood from the disclosure herein. In still other arrangements, the channel defining member can be replaced by a solid block or plate of material capable of being connected between studs and to vertically adjacent structures as described herein, in which case no separate mounting platform would be employed Additionally, the mounting platform can comprise an end plate on the lower end of the channel defining member, two end plates, or an intermediate plate bar orplura ty of bars extending across the channel between the ends of the channel defining member
The tie member 42 preferably comprises a tension resistant member, particularly a threaded rod in the illustrated embodiment The tie member 42 comprises a structural material, such as forged steel, having a diameter preferably between about 0 25 inch and 2 inches, and is about 0.75 inch in the illustrated embodiment. In other arrangements, the tension resistant member can comprise a cable The illustrated tie member 42 is fixed to the end plate 50, preferably by extending through a mounting aperture centered in the end plate 50 and applying a nut 52 on the distal or upper side of the end plate 50 The illustrated tie member 42 extends from the end plate 50, connected in tension resistant manner on the upper side of the end plate 50, through the channel of the channel defining member 40, through the bottom plate 32a and bottom track 34a, and into the concrete foundation 21 a If the mounting platform is located at the lower end or at an intermediate location in the channel-defining member, the nut is still located on the distal side of the channel defining member, but within the channel. In such an arrangement, the hollow, tubular nature of the channel defining member particularly facilitates access for the connection. The illustrated tie member 42 includes two coaxial members joined by a coupler 59, as will be better understood from the discussion of assembly below
While the illustrated channel defining member 40 and tie member 42 form a tension resistant connection, for some applications the connection can be tension and compression resistant. For this purpose, modification of the illustrated embodiment, where the tie member 42 comprises a stiff rod, can involve simple addition of a second nut on the proximal or bottom side of the end plate 50 More preferably, tension and compression resistance can be further enhanced by addition of a second mounting platform, such as a second end plate with nuts on the bottom or both sides fixing the tie member to the second end plate The tie member 42 can attach at the mounting platform by any suitable manner (e g welding, looping nut and washer, etc )
As noted, the channel defining member 40 is fixed to each of the end stud 22a and offset stud 24a between which it is sandwiched As disclosed in the '042 patent, bolts holes in the channel defining member 40 sidewalls are preferably staggered on either side of the tie member 42 that extends through the channel. A plurality of bolts 54 extend through each of the end stud 22a the bolt mounting apertures of the channel defining member 40 and the offset stud 24a The bolts 54 are then affixed by nuts 56, preferably on the side of the offset studs 24a, while bolt heads 58 preferably abut the end studs 22a As will be appreciated by the skilled artisan, in other arrangements, the channel defining member can be fixed to the studs 22a, 24a by means of other fasteners, such as nails, screws, rivets, etc. With reference now to Figures 3 5, the bottom track 34a is illustrated in more detail. For purposes of the present description, the longitudinal dimension of the track 34a extends across the lateral dimension of the shear wall 12a when assembled.
Referring initially to Figure 5, the track 34a is shown prior to assembly, comprising a strip of sheet metal, preferably between about 10 gauge and 30 gauge steel (16 gauge in the illustrated embodiment). The unassembled track 34a of Figure 5 illustrates three lateral zones, preferably separated by fold creases.
A first or central zone 60 comprises a plurality of longitudinally separated through holes 62. Desirably, the central zone 60 is wide enough to underlie the bottom plate 42 and sheet 20a (see Figure 3). As best seen from the sectional view of an assembled shear wall in Figure 4, the through holes 62 are formed by punching holes through the sheet metal, such that protrusions or flares 63 left by the punching process extend below the track 34a. The punched- through holes 62 preferably have a width or diameter between about 0.25 inch and 3 inches, more preferably between about 1 inch and 1.5 inches The holes 62 are preferably spaced by between about 1 inch and 12 inches, about 4 inches in the illustrated embodiment Through holes 62 at longitudinal ends of the track 34a, corresponding to lateral ends of the shear wall 12a, are preferably located to serve as templates for placement of the tie member 42, as will be better understood from the discussion of assembly below.
Referring again to Figure 5, the unassembled track 34a also comprises sidewall zones 64 on either lateral side of the central zone 60. Each sidewall zone 64 preferably comprises a plurality of fastener holes 66. As will be appreciated by the skilled artisans, such fastener holes 66 preferably have diameters between about 0.1 inch and 0.25 inch to facilitate nailing therethrough. In the illustrated embodiment, the fastener holes 66 are staggered between upper and lower portions of the sidewalls 64 to distribute stress.
With reference to Figures 4 and 6, a preferred method of assembling the shear 12a will now be described. Initially, partial building construction leaves a frame or opening for the shear wall 12a and a concrete form for the floor 21a. The track 34a is then positioned 100 and preferably temporarily fixed over the concrete form, either before pouring the concrete or after pouring and before hardening ("wet set"). In either case, the protrusions or flares 63 extend downwardly from the through holes 62 into wet concrete. At the same time, the tie members 42 are preferably extended 1 10 through selected through holes 62 at longitudinal ends of the track 34a, into the concrete form (also either prior to pouring or wet set within the concrete), protruding upwardly a few inches above the track 34a. The concrete is allowed to harden 120 around the protrusions 63 and the tie member 42.
The shear wall 12a is then erected 130 over the track 34a. The skilled artisan will appreciate that the wall 12a can be assembled during construction (on site assembly) or prior to erection 130 and tying to other elements of the building (pre manufactured assembly).
With reference to the embodiment of Figures 2A, 4 and 6, pre-manufactured assembly involves affixing the end and offset studs 22a, 24a, any intermediate studs 26a, top plates 28a, 30a and bottom plate 32a to the sheet
20a, preferably by nailing as described above Desirably, holes are drilled in appropriate spots for extending the tie members 42 therethrough The channel defining member 40 is bolted between the spaced pair of studs 22a, 24a. Once assembled the pre manufactured shear wall 12a can then be lifted or erected 130 into place over the track 34a. The tie members 42 protrude upwardly through holes in the bottom plate 32a. These tie members 42 can then be affixed 140 to the channel defining member 40, such as by coupling an extension to the portion of the members protruding through the track 34a and bottom plate 32a, and then threading the nut 52 over the member 42 until engaging the end plate 50
An exemplary on site assembly, in contrast involves first assembly the outside or end studs 22a, top plate 28a, 30a and bottom plate 32a This structure can be lifted into place within the frame or opening for the shear wall 12a, with the tie member 42 protruding upwardly through holes in the bottom plate 32a, and the shear wall 12a is braced in position The channel defining members 40 can be temporarily nailed in place inside the end studs 22a while bolt holes are drilled through the studs 22a The offset studs 24a are then inserted into the framework adjacent the channel defining members 40, the studs 24a are toe nailed into the plates 28a, 32a, and bolt holes are drilled through the offset studs 24a The tie member 42 can then be affixed 140 to the channel defining member 40, such as by coupling an extension to the portion of the member 42 protruding through the member. The wall sheet 20a can be last affixed and nailed to the various studs and plates while erected over the track 34a. Referring to Figures 4 6, following erection 130 of the shear wall 12a and fixing 140 the tie members 42 to the channel defining members 40, the track 34a preferably sheaths 150 the bottom edge of the shear wall 12a. In particular, the track 34a is folded along longitudinal crease lines separating the central zone 60 from the sidewall zones 64. The sidewall zones 64 are folded up 90° to the central zone 60, thereby forming a generally U-shaped track (see Figure 3) The sidewall zones 64 are affixed to the sheet 20a and bottom plate 32a, preferably by nailing through the fastener holes 66
While the embodiments above are described in the context of connecting a shear wall to a concrete foundation, the skilled artisan will appreciate that teachings herein are also applicable to other contexts.
Referring to Figure 7, for example, a the tie member 42 can be affixed to a mounting platform 50d of a first channel defining member 40d, such as by a nut 52d on a distal (upper) side of the platform 50d. As in the previously described embodiments, the channel defining member 40d is sandwiched between an end post or stud 22d and an offset stud 24d of a shear wall 12d The tie member 42 can be extended through a floor 21 d and affixed to a second channel-defining member 403 sandwiched between studs 22e, 24e of a shear wall 12e in the story below. The tie member 42 would then be affixed to a mounting platform 50e of the second channel-defining member 40e, such as by a nut 52e on a distal (lower) side of the platform 50e It will be understood that the tie member can be a single, continuous member, or it can comprises a plurality of coupled members (not shown).
Although the foregoing invention has been described in terms of certain preferred embodiments, other embodiments will be apparent to those of ordinary skill in the art. Accordingly, the present invention is not intended to be limited by the recitation of the preferred embodiments, but is instead to be defined by reference to the appended claims.

Claims

WE CLAIM:
1. A shear wall construction, comprising a wall sheet, a pair of generally vertical spaced studs affixed to a first side of the sheet at a lateral end of the sheet, a channel-defining member sandwiched between the studs, the channel-defining member configured to secure a tie member for extending parallel to the studs from the channel- defining member into a vertically-adjacent building structural member.
2. The shear wall construction of Claim 1 , further comprising a second pair of spaced studs at an opposite lateral end of the sheet.
3. The shear wall construction of Claim 2, further comprising a top plate and a bottom plate affixed to the first side of the sheet.
4. The shear wall construction of Claim 1 , further comprising a track sheathing a bottom edge of the wall sheet.
5. The shear wall construction of Claim 4, wherein the track comprises a central zone extending between two generally parallel track sidewalls, the central zone underlying the wall sheet and a bottom sill affixed to the first side of the sheet, one of the track sidewalls attached to the sheet on a second side of the sheet opposite the first side, and another of the track sidewalls attached to the first side of the bottom sill.
6. The shear wall construction of Claim 1 , wherein the wall sheet comprises plywood, the studs comprise two-by-four timbers, and the channel-defining member comprises structural metal.
7. The shear wall construction of Claim 1, wherein the spaced studs are horizontally separated by between about 2 inches and 3 inches.
8. The shear wall construction of Claim 1 , wherein the channel-defining member comprises a tubular member having an end plate with a mounting aperture for securing the tie member.
9. The shear wall construction of Claim 1 , wherein the channel-defining member is attached to the spaced studs via a plurality of bolts passing through each of the spaced studs and the channel-defining member sandwiched therebetween.
10. The shear wall construction of Claim 9, wherein the bolts pass through the channel-defining member on either side of a tie member axis.
1 1. The shear wall construction of Claim 10, wherein the channel-defining member includes a mounting platform extending across a channel, the mounting platform configured to secure the tie member.
12. The shear wall of Claim 1 1 , wherein the mounting platform comprises an end plate at one end of the channel, the end plate including a mounting aperture for securing a threaded rod therethrough and securing the threaded rod to the end plate with a nut.
13. A method of constructing a shear wall, comprising: providing a plywood sheet- attaching a pair of vertical studs, horizontally spaced from one another by between about 1 inch and 6 inches, to one side of the sheet proximate a lateral end of the sheet; and affixing a channel-defining member between the pair of studs, the channel-defining member including a mounting platform configured to mount an elongated tie member.
14. The method of Claim 13, wherein the mounting platform comprises an end plate.
15. The method of Claim 13, further comprising attaching a second pair of vertical studs, horizontally space from one another by between about 1 inch and 6 inches, to the sheet proximate an opposite lateral end of the sheet.
16. The method of Claim 15, further comprising attaching a generally horizontal top plate to the one side of the sheet proximate a top edge of the sheet.
17. The method of Claim 15, further comprising attaching a generally horizontal bottom plate to the one side of the sheet proximate a bottom edge of the sheet.
18. The method of Claim 17, further comprising sheathing the bottom plate with a track.
19. The method of Claim 18, wherein sheathing comprises: folding sheet metal to form a central zone with upwardly extending sidewalls; and attaching the sidewalls to a front side of the sheet and a back side of the bottom plate, the central zone extending along a bottom side of the bottom plate.
20. The method of Claim 19, further comprising embedding protrusions from the track in concrete prior to sheathing the bottom plate.
21. The method of Claim 13, wherein affixing the channel-defining member comprises extending each of a plurality of bolts through both of the pair of studs and through the channel-defining member therebetween.
22. The method of Claim 13, wherein the channel-defining member is affixed to orient its channel generally parallel to the pair of studs.
23. A method of assembling a shear wall, comprising: attaching a first pair of vertical, spaced studs to a back side of a wall sheet proximate a first lateral end of the wall sheet; attaching a second pair of vertical, spaced studs to the back side of the wall sheet proximate a second lateral end of the wall sheet; attaching a horizontal top plate to the back side of the wall sheet proximate a top end of the wall sheet; attaching a horizontal bottom plate to the back side of the wall sheet proximate a bottom end of the wall sheet; sandwiching a channel-defining member between each of the pairs of vertical, spaced studs; and sheathing the bottom end of the wall sheet with a track after attaching the bottom plate, the track including protrusions extending away from a bottom end of the bottom plate.
24. The method of Claim 23, further comprising placing the track over a concrete form, pouring concrete into the concrete form and hardening the concrete around the protrusions of the metal track. 25 The method of Claim 24, further comprising extending a tie member through the track into the concrete form prior to hardening the concrete
26 The method of Claim 25, wherein extending the tie member through the track into the concrete form is conducted after pouring the concrete 27 The method of Claim 24, wherein sheathing the bottom end of the wall sheet is performed after hardening the concrete around the horizontal bottom plate
28 The method of Claim 24, further comprising extending a threaded rod from the channel-defining member to the concrete form affixing the threaded rod to the channel-defining member and the concrete
29 The method of Claim 28 wherein affixing the threaded rod to the channel defining member comprises passing the threaded rod through an aperture in a mounting platform of the channel defining member and fixing the threaded rod to the mounting platform
30 A track elongated along a longitudinal axis, comprising two sidewalls extending longitudinally and having a central zone between the sidewalls, the central zone including a plurality of punched-through holes, the sidewalls including a plurality of nail holes 31 The track of Claim 30, wherein the punched through holes extend into downwardly extending protrusions
32 The track of Claim 30, wherein the punched-through holes have widths between about 0.25 inch and 3 inches
33 The track of Claιm30 wherein the punched through holes are spaced by between about 1 inch and 12 inches
34 The track of Claim 30, wherein the nail holes have diameters between about 0.1 inch and 0.25 inch.
35 The track of Claim 30 further comprising a fold crease extending longitudinally between each sidewall and the central zone 36 The track of Claim 30, wherein the central zone has a lateral width sized for sheathing a wall sheet and a bottom plate running along the lower end of a shear wall.
37 The track of Claim 30, extending around the lower edge of a prefabricated shear wall.
38 The track of Claim 30, wherein the nail holes are staggered along upper and lower portions of each sidewall.
PCT/US2000/034107 2000-01-06 2000-12-15 Shear wall construction WO2001049949A2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU21061/01A AU2106101A (en) 2000-01-06 2000-12-15 Shear wall construction

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
US09/479,314 US6389767B1 (en) 2000-01-06 2000-01-06 Shear wall construction
US09/479,314 2000-01-06

Publications (2)

Publication Number Publication Date
WO2001049949A2 true WO2001049949A2 (en) 2001-07-12
WO2001049949A3 WO2001049949A3 (en) 2001-12-13

Family

ID=23903501

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/US2000/034107 WO2001049949A2 (en) 2000-01-06 2000-12-15 Shear wall construction

Country Status (3)

Country Link
US (6) US6389767B1 (en)
AU (1) AU2106101A (en)
WO (1) WO2001049949A2 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103790267A (en) * 2014-02-19 2014-05-14 天津大学建筑设计研究院 Reinforcement type prefabricated assembly type shear wall structure and construction method thereof
NL2020320B1 (en) * 2018-01-25 2019-07-31 Van Hove Holding B V System and method for anchoring a wall part to a floor

Families Citing this family (45)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6389767B1 (en) * 2000-01-06 2002-05-21 Zone Four, Llc Shear wall construction
US7150132B2 (en) * 2003-08-12 2006-12-19 Commins Alfred D Continuous hold-down system
US6625945B2 (en) 2000-08-08 2003-09-30 Alfred D. Commins Balanced, multi-stud hold-down
US6862854B1 (en) 2000-08-14 2005-03-08 Simpson Strong-Tie Company, Inc. Single-piece continuity tie
US6560940B2 (en) * 2000-08-18 2003-05-13 Lee W. Mueller Two-piece clinched plate tension/compression bracket
US20060194495A1 (en) * 2001-02-20 2006-08-31 Lubker John W Ii Protective drainage wraps
US6869901B2 (en) * 2001-02-20 2005-03-22 Pactiv Corporation Protective drainage wraps
US20060194494A1 (en) * 2001-02-20 2006-08-31 Lubker John W Ii Protective drainage wraps
US9656445B2 (en) 2001-02-20 2017-05-23 Kingspan Insulation Llc Protective drainage wraps
US6550212B2 (en) * 2001-02-20 2003-04-22 Pactiv Corporation Protective drainage wraps
US8082703B2 (en) * 2002-02-11 2011-12-27 Ei-Land Corporation Force-resisting devices and methods for structures
US7043879B2 (en) * 2002-02-11 2006-05-16 Ei-Land Corporation Force-resisting devices and methods for structures
US8127502B2 (en) * 2002-08-06 2012-03-06 EI-Land Corp. Building structure configured to exhibit a prescribed load-deflection relationship when a force is applied thereto
US7634888B2 (en) 2003-10-07 2009-12-22 Trussed, Inc. Load-resisting truss segments for buildings
US7117648B1 (en) 2003-10-21 2006-10-10 John Duncan Pryor Cross tie connection bracket
US20050086905A1 (en) * 2003-10-22 2005-04-28 Dietrich Industries, Inc. Shear wall panel
US20050086895A1 (en) * 2003-10-27 2005-04-28 Elliot A. C. Compression post for structural shear wall
US7445192B2 (en) * 2004-06-14 2008-11-04 Simpson Strong-Tie Company, Inc. Shear wall template
US7506479B2 (en) * 2004-08-17 2009-03-24 Simpson Strong-Tie Company, Inc. Shear transfer plate
US8056301B2 (en) * 2004-12-23 2011-11-15 Specialty Hardware L.P. Method of framing a building shear wall structure compatible with conventional interior or exterior finishing materials and subsurface panel for use therewith
US7752824B2 (en) * 2005-03-14 2010-07-13 Mitek Holdings, Inc. Shrinkage-compensating continuity system
US8327592B2 (en) 2005-08-05 2012-12-11 Lafferty Iii George A Structural reinforcing system components
US20060142402A1 (en) * 2006-03-18 2006-06-29 Mr. Clarence Dunnrowicz Improved Robustness Wood Post Achoring Method
US7934347B2 (en) * 2006-07-28 2011-05-03 Paul Brienen Coupling beam and method of use in building construction
US8356449B2 (en) * 2006-10-18 2013-01-22 Jin-Jie Lin Floor span connector
US20080104894A1 (en) * 2006-11-07 2008-05-08 Kramer William J Pre-fabricated post frame panel
US8689518B2 (en) * 2007-03-06 2014-04-08 Bay City Flower Company, Inc. Continuity tie for prefabricated shearwalls
US20090007507A1 (en) * 2007-07-06 2009-01-08 James Zhai Energy efficient assembly building construction using light-gage metal studs and concrete slabs
US8281541B2 (en) * 2008-09-05 2012-10-09 Mitek Holdings, Inc. Hold down connector
US8448387B2 (en) * 2009-09-01 2013-05-28 Integrity Wall, LLC Wall panel and method
US10112576B2 (en) 2011-11-18 2018-10-30 Joyson Safety Systems Acquisition Llc Seatbelt retractor
JP5995466B2 (en) * 2012-03-12 2016-09-21 住友林業株式会社 Wooden building structure
US8881478B2 (en) 2012-06-22 2014-11-11 Simpson Strong-Tie Company, Inc. Ratcheting take-up device
JP6202931B2 (en) * 2013-08-06 2017-09-27 住友林業株式会社 Connecting member, manufacturing method of connecting member, and wood member joining structure
CN103556753A (en) * 2013-10-08 2014-02-05 沈阳建筑大学 Tooth-form connecting method of prefabricated integral shear wall and beam
US9394706B2 (en) 2013-10-08 2016-07-19 Simpson Strong-Tie Company, Inc. Concrete anchor
JP2015101850A (en) * 2013-11-22 2015-06-04 株式会社グレイプ Framework wall structure, building, and framework wall building construction
US9163655B2 (en) 2014-01-14 2015-10-20 Kaoru Taneichi Thrust nut
MX368074B (en) 2015-01-23 2019-09-17 Mitek Holdings Inc Insulated panel assembly.
US9464427B2 (en) 2015-01-23 2016-10-11 Columbia Insurance Company Light gauge steel beam-to-column joint with yielding panel zone
US9428902B1 (en) 2015-06-12 2016-08-30 Randall John LoFranco Bracket for multi-story buildings
US10335620B2 (en) 2016-12-12 2019-07-02 ScotBilt Homes, Inc. Methods of making manufactured housing components and manufactured homes
CA3088299A1 (en) * 2018-01-10 2019-07-18 Jencol Innovations, Llc Thermal break for concrete slabs
CN108590300B (en) * 2018-03-30 2019-11-12 东南大学 Self-resetting metal energy consumption drag-line
PE20211099A1 (en) 2018-08-21 2021-06-15 John David Wright INSULATING AND INSULATING FRAME APPARATUS AND METHODS OF MANUFACTURING AND USE OF THE SAME

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2692408A (en) * 1948-11-16 1954-10-26 Thomas F Connor Prefabricated building construction
US5228261A (en) * 1991-10-15 1993-07-20 Watkins Robert P Floor joist hanger
US6006487A (en) * 1998-01-09 1999-12-28 Simpson Strong-Tie Co., Inc. Loadbearing wall holdown

Family Cites Families (49)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE476638C (en) * 1929-05-22 Heinrich Tigges Self-closing lock, especially for the compartment doors of passenger cars
US1054175A (en) 1909-12-28 1913-02-25 Nat Malleable Castings Co Timber-pocket.
US1474660A (en) 1921-12-02 1923-11-20 William E White Form support
US2281402A (en) * 1939-10-12 1942-04-28 Homasote Company Inc Framing construction
US2316425A (en) * 1940-08-01 1943-04-13 Prebilt Housing Corp Combination doorframe and casing
US3156018A (en) * 1961-12-21 1964-11-10 John H Slayter Plant-manufactured building structure
US3224533A (en) * 1962-12-31 1965-12-21 Inland Steel Products Company Opening frame and clip therefor
US3234841A (en) * 1963-05-09 1966-02-15 Adams Co J D Gusset plate
US3263381A (en) * 1963-10-28 1966-08-02 Rafters Inc Building frame structure
US3264021A (en) 1963-11-26 1966-08-02 John R Artman Connecting member for structural units
US3587443A (en) * 1969-10-15 1971-06-28 Jerry Rapport Vent screen assembly
US3837754A (en) 1971-06-21 1974-09-24 Swingline Inc Corner support structure and cap member utilized in connection with same
USRE31234E (en) * 1972-11-06 1983-05-10 Gang-Nail Systems, Inc. Hinged connector plate
DE2704954A1 (en) 1977-02-07 1978-08-10 Otto Prof Dipl Ing D Jungbluth SPATIAL STRUCTURAL STRUCTURE OF BARS AND NODE BODIES
US4129975A (en) 1977-03-09 1978-12-19 Matrix Toys, Inc. Construction set having clip fasteners
US4611948A (en) 1979-08-09 1986-09-16 Johnson Lawrence N Boat trailer with pivotal dropped crossbar rolled mounting system
US4648216A (en) * 1983-07-26 1987-03-10 Gang-Nail Systems Inc. Prefabricated building
US4616950A (en) 1984-01-31 1986-10-14 Morris Tom C Timber joining devices
US4656792A (en) * 1984-03-07 1987-04-14 Clark Gerald L Truss building system
PH18815A (en) 1984-12-11 1985-10-02 Jose S Orosa Knockdown furnitures and the structural component therefor
US4639176A (en) * 1986-01-21 1987-01-27 Smith Glenn C Truss plate
US4893961A (en) 1989-06-05 1990-01-16 Trus Joist Corporation Joist hanger
US5094059A (en) * 1990-04-06 1992-03-10 Poloron Homes Of Pennsylvania, Inc. Hinged roof truss and double hinge therefor
DE4029726A1 (en) 1990-09-20 1992-03-26 Jens Dethloff METHOD FOR JOINING WOODEN PARTS AND JOINING WOODEN PARTS
US5092096A (en) 1990-12-13 1992-03-03 Cornell James C Temporary bridge joist support bracket
JPH07111094B2 (en) 1991-12-27 1995-11-29 小野 辰雄 Prop device
US5353560A (en) * 1992-06-12 1994-10-11 Heydon Building Systems International, Limited Building structure and method of use
US5249404A (en) 1992-05-11 1993-10-05 Simpson Strong-Tie Company, Inc. Holdown connection
FI923118A0 (en) 1992-07-07 1992-07-07 Tuomo Juola Building framework.
JP3230305B2 (en) * 1992-12-08 2001-11-19 株式会社大林組 Construction method of steel plate concrete wall
US5375384A (en) * 1993-01-22 1994-12-27 Wolfson; Yehuda Holdown apparatus for a shear wall
CA2134137A1 (en) 1993-10-30 1995-05-01 Goto Yasuo Connector for truss structure
US5531052A (en) * 1993-12-28 1996-07-02 Agar; Robert S. Unitary suspension clip for supporting partition walls
US6205725B1 (en) * 1994-08-29 2001-03-27 Michael Butler Interlocking corrugated panel wall cast in-situ
US5813181A (en) 1995-08-21 1998-09-29 Ashton; Roger Wall Continuity tie
US5809719A (en) 1995-08-21 1998-09-22 Ashton; Roger Wall Manually adjustable structural load transferring device
US5706626A (en) * 1995-12-14 1998-01-13 Mueller; Lee W. Pre-assembled internal shear panel
JPH09165871A (en) * 1995-12-15 1997-06-24 Ado Space Kk Frame member
US5729950A (en) 1996-04-03 1998-03-24 Hardy Industries, Inc. All-metal reinforcing building frame
US5765333A (en) * 1996-04-03 1998-06-16 Cunningham; Dale W. Unitized post and panel building system
US6158184A (en) * 1997-04-14 2000-12-12 Timmerman, Sr.; Timothy L Multi-pane lateral force resisting system
US7251920B2 (en) * 1997-04-14 2007-08-07 Timmerman Sr Timothy L Lateral force resisting system
US5867963A (en) * 1997-09-23 1999-02-09 Truswal Systems Corporation Trimmable truss apparatus
US6256960B1 (en) * 1999-04-12 2001-07-10 Frank J. Babcock Modular building construction and components thereof
AU2482001A (en) 1999-10-15 2001-04-30 Thomas Leung Shear wall panel
CA2285890C (en) * 1999-10-15 2003-08-26 Tlse Engineering Inc. Shear wall panel
US6389767B1 (en) * 2000-01-06 2002-05-21 Zone Four, Llc Shear wall construction
US6625945B2 (en) * 2000-08-08 2003-09-30 Alfred D. Commins Balanced, multi-stud hold-down
US6931804B2 (en) * 2001-06-21 2005-08-23 Shear Force Wall Systems Inc. Prefabricated shearwall having improved structural characteristics

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US2692408A (en) * 1948-11-16 1954-10-26 Thomas F Connor Prefabricated building construction
US5228261A (en) * 1991-10-15 1993-07-20 Watkins Robert P Floor joist hanger
US6006487A (en) * 1998-01-09 1999-12-28 Simpson Strong-Tie Co., Inc. Loadbearing wall holdown

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103790267A (en) * 2014-02-19 2014-05-14 天津大学建筑设计研究院 Reinforcement type prefabricated assembly type shear wall structure and construction method thereof
NL2020320B1 (en) * 2018-01-25 2019-07-31 Van Hove Holding B V System and method for anchoring a wall part to a floor

Also Published As

Publication number Publication date
US7171789B2 (en) 2007-02-06
US20070137125A1 (en) 2007-06-21
US7849647B2 (en) 2010-12-14
US7559178B2 (en) 2009-07-14
US6389767B1 (en) 2002-05-21
US20100011692A1 (en) 2010-01-21
US6826882B2 (en) 2004-12-07
US20050072117A1 (en) 2005-04-07
US6564519B2 (en) 2003-05-20
US20030115824A1 (en) 2003-06-26
WO2001049949A3 (en) 2001-12-13
US20020108331A1 (en) 2002-08-15
AU2106101A (en) 2001-07-16

Similar Documents

Publication Publication Date Title
US6826882B2 (en) Shear wall construction
US8327592B2 (en) Structural reinforcing system components
US6067769A (en) Reinforcing brace frame
US7716899B2 (en) Building construction systems and methods
US4473209A (en) Prefabricated wall form modular unit
US20150121775A1 (en) Light weight modular units for staggered stacked building system
US6665992B2 (en) Concrete construction block and method for forming the same
US8297023B2 (en) Stackable column assemblies and methods of construction
US20030084629A1 (en) Ring beam/lintel system
SK136593A3 (en) Sheet metal structural member construction panel and method of construction
US20100005749A1 (en) Steel building frame system
US4809480A (en) Building metal support apparatus and method
US20050229509A1 (en) Structural braced frame wall panel system
US7325362B1 (en) Steel roof truss system
US20080016793A1 (en) Web hole reinforcing for metal wall stubs
US6098360A (en) Offset web composite beam
US20030101675A1 (en) Building frame bracing panel and method
US6256951B1 (en) Lateral bracing system
JP3764020B2 (en) Steel frame structure
JPH0868113A (en) Connecting structure for steel beam and reinforced concrete beam
JP4551010B2 (en) Steel foundation structure using channel steel
JP2522708B2 (en) Reinforcing bar tip assembly beam with formwork and reinforcing bar tip assembly method with formwork
KR102289243B1 (en) Underground Parking Lot Construction Method Using Pre-assembled bar column, U-shaped beam, Corrugated deck
JPH10317563A (en) Lintel, roof beam, floor beam, and sill
WO2020024010A1 (en) Structure adapted to span supports

Legal Events

Date Code Title Description
AK Designated states

Kind code of ref document: A2

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BY BZ CA CH CN CR CU CZ CZ DE DE DK DK DM DZ EE EE ES FI FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NO NZ PL PT RO RU SD SE SG SI SK SK SL TJ TM TR TT TZ UA UG UZ VN YU ZA ZW

AL Designated countries for regional patents

Kind code of ref document: A2

Designated state(s): GH GM KE LS MW MZ SD SL SZ TZ UG ZW AM AZ BY KG KZ MD RU TJ TM AT BE CH CY DE DK ES FI FR GB GR IE IT LU MC NL PT SE TR BF BJ CF CG CI CM GA GN GW ML MR NE SN TD TG

121 Ep: the epo has been informed by wipo that ep was designated in this application
AK Designated states

Kind code of ref document: A3

Designated state(s): AE AG AL AM AT AU AZ BA BB BG BR BY BZ CA CH CN CR CU CZ CZ DE DE DK DK DM DZ EE EE ES FI FI GB GD GE GH GM HR HU ID IL IN IS JP KE KG KP KR KZ LC LK LR LS LT LU LV MA MD MG MK MN MW MX MZ NO NZ PL PT RO RU SD SE SG SI SK SK SL TJ TM TR TT TZ UA UG UZ VN YU ZA ZW

AL Designated countries for regional patents

Kind code of ref document: A3

Designated state(s): GH GM KE LS MW MZ SD SL SZ TZ UG ZW AM AZ BY KG KZ MD RU TJ TM AT BE CH CY DE DK ES FI FR GB GR IE IT LU MC NL PT SE TR BF BJ CF CG CI CM GA GN GW ML MR NE SN TD TG

REG Reference to national code

Ref country code: DE

Ref legal event code: 8642

122 Ep: pct application non-entry in european phase
NENP Non-entry into the national phase

Ref country code: JP